PROJECT STATUS: DESIGN


Project Description 

The City of Alexandria is currently designing repairs for a damaged 10-inch sanitary sewer main along N. Pitt Street, between Cook Street and Pendleton Street. The damage was identified after receiving resident complaints about the sewer backups from multiple households. CCTV inspection of the sanitary sewer recorded structural damage at the invert of the 10-inch RCP. The solution under design may include the separation of sewer laterals from the combined sewer line and then connection to the 10-inch PVC sanitary sewer line along the N. Pitt Street.  


121392500-Block N Pitt Sewer Separation-Map-20210325

Area Map of 500 Block N Pitt St Sewer Separation Project Location


Schedule 

Design 

January – September 2021 

Construction 

September – December 2021 

Additional Resources