Potomac Yard Metrorail Station Construction Updates Archive

Page updated on Aug 27, 2021 at 4:39 PM

Construction Updates Archive

The following posts have been pulled directly from the Construction web page. Images have been reduced in size; however, the full-size image is available by clicking on the thumbnail. 

August 2021

AuGust 6, 2021 UPDATE

Construction Work

The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 


AC Switchgear Building

Activity: Mounting junction boxes & starting conduit install.      

  • Timeframe: Ongoing

Activity: Installation of door frames and CMU chalking and interior touch up painting.                                                              
  • Timeframe: Early-August


Duct Banks

Activity: Excavation and installation of duct banks (north end of station) (pour, strip duct bank frame, and back fill).

  • Timeframe: Ongoing


North Pavilion

Activity: Installation of electrical and plumbing anchors and installation

  • Timeframe: Ongoing


Activity: Install under roof deck drain pipe and conduit     

  • Timeframe: Ongoing


Pedestrian Bridge 

Activity: Installation of conduit and decking (from Knuckle to Headhouse)

  • Timeframe: Ongoing

Activity: Southwest: Form and pour pier columns and stems.

  • Timeframe: Ongoing


Site Work

Activity: South End: Installation of storm drain system (pipes and manholes)

  • Timeframe: Ongoing


Activity: North End: Excavate for NE emergency ramps and storm drain system

  • Timeframe: Ongoing


South Pavilion  

Activity: No Activity

  • Timeframe:   


Station Headhouse

Activity: Mezzanine Level: Installation of roof decking; Continued bolting and steel welding

  • Timeframe: Ongoing


Activity: Platform Level: Roof Installation 

  • Timeframe: Ongoing

Activity: Basement Level: Installation of conduit in crawlspace, FSP, plumbing, and electrical conduit

  • Timeframe: Ongoing


Activity: Curtain wall frame assembly and layout of connections

  • Timeframe: Ongoing


Station Platform

Activity: Installation of drain pipe under direct fixation slab and fire piping

  • Timeframe: Ongoing

Activity: Weld, bolt and deck.

  • Timeframe: Ongoing

 
 2601 Main Line Blvd.

Activity: Sub-contractor work trailer

  • Timeframe: Ongoing
  • Note: Generator in use to supply power to trailers.


Activity: Worker van service to/from construction site

  • Timeframe: Ongoing

Activity: Construction material staging

  • Timeframe: Ongoing


July 2021

July 2, 2021 UPDATE

Construction Work

The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

AC Switchgear Building
Activity: Interior touch up painting; mounting of junction boxes; conduit installation, applying floor sealer, & vapor barrier installation      

  • Timeframe: Ongoing

Activity: Preparations for installation of brick veneer.     
  • Timeframe: Ongoing


Duct Banks

Activity: Excavation and installation of communication, ATC, and TP duct banks (north end of station) (pour and strip duct bank)

  • Timeframe: Ongoing


North Pavilion

Activity: Install waterproofing & drain board, installation of drywall, insulation, electrical and plumbing anchors

  • Timeframe: Ongoing


Activity: Install under roof deck drain pipe and conduit     

  • Timeframe: Ongoing


Pedestrian Bridge 

Activity: Installation of conduit and decking (from Knuckle to Headhouse)

  • Timeframe: Ongoing

Activity: Southwest: Pour foundation pier

  • Timeframe: Ongoing


Site Work

Activity: South End: Installation of storm drain system (pipes and manholes)

  • Timeframe: Ongoing


Activity: North End: Excavate for NE emergency ramps and storm drain system

  • Timeframe: Ongoing


South Pavilion  

Activity: Pour grade beam and pile caps  

  • Timeframe: Through early July  


Station Headhouse

Activity: Mezzanine Level: Installation of roof decking, and escalator roof; continued bolting and steel welding

  • Timeframe: Ongoing


Activity: Platform Level: Installation of dowel for CMU block and clips, & roof installation

  • Timeframe: Ongoing

Activity: Basement Level: Installation of conduit in crawlspace, FSP, plumbing, and electrical conduit

  • Timeframe: Ongoing

Activity: Station steel erection

  • Timeframe: Ongoing

Activity: Curtain wall frame assembly and layout of connections

  • Timeframe: Ongoing


Station Platform

Activity: Installation of rebar for direct fixation slab and first slab pour

  • Timeframe: Ongoing

Activity: Platform steel erection

  • Timeframe: Ongoing


Station Platform

Activity: Installation of rebar for direct fixation slab and stray current bonding

  • Timeframe: Ongoing

Activity: Installation of HDPE drain pipe, catch basins, and granular fill

  • Timeframe: Ongoing


2601 Main Line Blvd.

Activity: Sub-contractor work trailer

  • Timeframe: Ongoing
  • Note: Generator in use to supply power to trailers.


Activity: Worker van service to/from construction site

  • Timeframe: Ongoing

Activity: Construction material staging

  • Timeframe: Ongoing


June 2021

JUNE 24, 2021 UPDATE

Construction Work

The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

AC Switchgear Building
Activity: Interior touch up painting; mounting of junction boxes; conduit installation, vapor barrier installation   

  • Timeframe: Ongoing

Activity: Preparations for installation of brick veneer.     
  • Timeframe: Ongoing


Duct Banks

Activity: Excavation and installation of communication, ATC, and TP duct banks (north end of station)

  • Timeframe: Ongoing


North Pavilion

Activity: Performing interior concrete finish work

  • Timeframe: Ongoing


Pedestrian Bridge 

Activity: Stud welding of piles; form work of pier/pile cap foundation; pouring of pier footings; installation of rebar for grade beams

  • Timeframe: Ongoing

Activity: Installation of conduit and decking (from Knuckle to Headhouse)

  • Timeframe: Ongoing


Site Work

Activity: South End: Installation of storm drain system (pipes and manholes)

  • Timeframe: Ongoing


South Pavilion  

Activity: Installation of rebar for foundation  

  • Timeframe: Through early July  


Station Headhouse

Activity: Mezzanine Level: Installation of roof decking, and escalator roof.  Installation of mezzanine soffit anchors, conduits, edge forms

  • Timeframe: Ongoing


Activity: Platform Level: Installation of dowel for CMU block and clips, & roof installation

  • Timeframe: Ongoing

Activity: Basement Level: Installation of conduit in crawlspace, FSP, plumbing, and HVAC piping.

  • Timeframe: Ongoing

Activity: Station steel erection

  • Timeframe: Ongoing

Activity: Curtain wall fabrication and stud welding

  • Timeframe: Ongoing


Station Platform

Activity: Installation of rebar for direct fixation slab and first slab pour

  • Timeframe: Ongoing

Activity: Platform steel erection

  • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    ALL PRIOR CONSTRUCTION UPDATES CAN BE FOUND IN THE CONSTRUCTION UPDATES ARCHIVE.


    Construction Photo Gallery

    Recent Activity

    The following are photos from construction of the Potomac Yard Metrorail Station:

    New images coming soon


    View A Collection of Photos from the First Year of Construction


    JUNE 17, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Interior touch up painting; mounting of junction boxes; conduit installation, vapor barrier installation   

    • Timeframe: Ongoing

    Activity: Preparations for installation of brick veneer.     
    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing


    North Pavilion

    Activity: Preparations for mezzanine slab pour

    • Timeframe: Ongoing


    Pedestrian Bridge/Knuckle Pier

    Activity: Stud welding of piles; form work of pier/pile cap foundation; pouring of pier footings; installation of rebar for grade beams

    • Timeframe: Ongoing

    Activity: Installation of conduit and decking

    • Timeframe: Ongoing


    Site Work

    Activity: South End: Installation of storm drain system (pipes and manholes)

    • Timeframe: Ongoing


    Activity: Track Right-of-Way: Installation of communication troughs

    • Timeframe: Through late June


    South Pavilion  

    Activity: Installation of foundation forms  

    • Timeframe: Through mid-June  


    Station Headhouse

    Activity: Mezzanine Level: Installation of roof decking, and escalator roof.  Installation of mezzanine soffit anchors, conduits, edge forms

    • Timeframe: Ongoing


    Activity: Platform Level: Forming and pouring behind duct bank, installation of dowel for CMU block and clips, & roof installation

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, FSP, plumbing, and HVAC piping.

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing

    Activity: Curtain wall fabrication and stud welding

    • Timeframe: Ongoing


    Station Platform

    Activity: Installation of rebar for direct fixation slab and stray current bonding

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of curb

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    JUNE 10, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Interior painting; mounting of junction boxes; conduit installation   

    • Timeframe: Ongoing

    Activity: Preparations for installation of brick veneer.   
      
    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing


    North Pavilion

    Activity: Preparations for mezzanine slab pour

    • Timeframe: Ongoing


    Pedestrian Bridge/Knuckle Pier

    Activity: Stud welding of piles; form work of pier/pile cap foundation

    • Timeframe: Ongoing

    Activity: Installation of conduit and decking

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Installation of foundation forms  


    Station Headhouse

    Activity: Mezzanine Level: CMU block insulation; CMU support angles, vapor barrier, and ceiling drywall installation; curtain wall preparation for connections

    • Timeframe: Ongoing


    Activity: Platform Level: Forming and pouring behind duct bank, installation of dowel for CMU block and clips

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, FSP, plumbing, and HVAC piping.

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing

    Activity: Curtain wall fabrication and stud welding

    • Timeframe: Ongoing


    Station Platform

    Activity: Installation of rebar for direct fixation slab and stray current bonding

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of curb

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    JUNE 3, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Interior painting; mounting of junction boxes; conduit installation   

    • Timeframe: Ongoing

    Activity: Installation of the roof.  
    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing


    North Pavilion

    Activity: CMU block/insulation installation in ground level escalator mechanical room; under roof deck conduit installation; curtain wall frame fabrication

    • Timeframe: Ongoing


    Pedestrian Bridge/Knuckle Pier

    Activity: Stud welding of piles; form work of pier/pile cap foundation

    • Timeframe: Ongoing

    Activity: Installation of conduit and decking

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Installation of foundation forms  


    Station Headhouse

    Activity: Mezzanine Level: CMU block insulation; CMU support angles, vapor barrier, and ceiling drywall installation; curtain wall preparation for connections

    • Timeframe: Ongoing


    Activity: Platform Level: Roof slab stripping and forming; Form and install rebar for stair support walls 

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, CMU wall and ceiling insulation

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Setting sub-base for direct fixation slab

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of edge light conduit

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing



    May 2021

    May 27, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Interior painting, mounting junction boxes & continuing with conduit installation.   

    • Timeframe: Ongoing

    Activity: Installation of the roof.  

    • Timeframe: Ongoing

     

    North Pavilion  
    Activity: Set rebar, install CMU block/Insulation in ground level escalator mechanical room, and install under roof deck conduit.

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Installation of foundation forms  


    Station Headhouse

    Activity: Mezzanine Level: CMU block insulation, installation of CMU support angles, vapor barrier, and ceiling drywall

    • Timeframe: Ongoing


    Activity: Platform Level: Form and install rebar for stair support walls 

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, CMU wall and ceiling insulation

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Setting sub-base for direct fixation slab

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of edge light conduit

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing 


    Pedestrian Bridge/Knuckle Pier

    Activity: Stud welding of piles; form work of pier/pile cap foundation

    • Timeframe: Ongoing

    Activity: Installation of conduit and decking

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    Construction Gallery

    View A Collection of Photos Illustrating one Year of Construction


    The following are photos from construction of the Potomac Yard Metrorail Station:

    PYMS Construction - North Pavilion - Southwest Corner 2021-04-15

    North Pavilion, Southwest Corner


    PYMS Construction - South Pavilion - Pile Driving 2021-04-15

    Pile Driving for South Pavilion 


    PYMS Construction - Platform - Drainage System Installation 2021-04-15

    Platform Drainage System Installation


    PYMS Construction - Station Headhouse - Structural Steel Installation 2021-04-15

    Station Headhouse Structural Steel Installation


    PYMS Construction - Pedestrian Bridge - Decking Installation 2021-04-14

    Pedestrian Bridge Decking Installation


    May 13, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Apply block filler on CMU walls, Interior painting, mounting junction boxes & continuing with conduit installation.   

    • Timeframe: Ongoing

    Activity: Installation of vapor barrier on the roof, cover board, and EPDM membrane.  

    • Timeframe: Ongoing

     

    North Pavilion  
    Activity: Set rebar, install CMU block/Insulation in ground level escalator mechanical room, and install under roof deck conduit.

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Production pile driving and form grade beam and pile caps  


    Station Headhouse

    Activity: Mezzanine Level: CMU block insulation, installation of CMU support angles, vapor barrier, and ceiling drywall

    • Timeframe: Ongoing


    Activity: Platform Level: Form and install rebar for stair support walls 

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, CMU wall and ceiling insulation

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Install HDPE drain pipe, catch basins and granular fill

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of edge light conduit

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing 


    Pedestrian Bridge/Knuckle Pier

    Activity: Installation of foundation rebar for south pavilion bridge piers 

    • Timeframe: Ongoing

    Activity: Bolt and splice plates in preparation for lowering of bridge

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    May 6, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Interior painting, hanging conduits, installation of scaffolding  

    • Timeframe: Ongoing

     

    North Pavilion  
    Activity: Backfilling, installation of mezzanine deck rebar

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Production pile driving


    Station Headhouse

    Activity: Mezzanine Level: Block insulation, installation of CMU support angles, vapor barrier, and ceiling drywall

    • Timeframe: Ongoing


    Activity: Platform Level: Installation of roof shoring, reinforcing, and pouring of roof

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, CMU wall and ceiling insulation

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Installation of platform steel

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of slab rebar

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing 


    Pedestrian Bridge/Knuckle Pier

    Activity: Installation of foundation rebar for south pavilion bridge piers 

    • Timeframe: Ongoing

    Activity: Bolt and splice plates in preparation for lowering of bridge

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing



    April 2021

    April 15, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: CMU wall installation and interior wall patching  

    • Timeframe: Ongoing

     

    North Pavilion  
    Activity: Wall and mezzanine deck pours

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Production pile driving


    Station Headhouse

    Activity: Mezzanine Level: Preparations for roof slab pours

    • Timeframe: Ongoing


    Activity: Platform Level: Wall and roof pours

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, CMU walls, ceiling insulation, and escalator supports

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Between platforms: Installation of drainage system 

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of corridor hangers, racks, conduits, and curbs 

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing 


    Pedestrian Bridge/Knuckle Pier


    Activity: Splicing plates; installation of bridge decking and under-deck conduit

    • Timeframe: Ongoing


    2601 Main Line Blvd.

    Activity: Sub-contractor work trailer

    • Timeframe: Ongoing
    • Note: Generator in use to supply power to trailers.


    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    Construction Gallery

    View A Collection of Photos Illustrating one Year of Construction


    The following are photos from construction of the Potomac Yard Metrorail Station:

    PYMS Construction - North Pavilion - Southwest Corner 2021-04-15

    North Pavilion, Southwest Corner


    PYMS Construction - South Pavilion - Pile Driving 2021-04-15

    Pile Driving for South Pavilion 


    PYMS Construction - Platform - Drainage System Installation 2021-04-15

    Platform Drainage System Installation


    PYMS Construction - Station Headhouse - Structural Steel Installation 2021-04-15

    Station Headhouse Structural Steel Installation


    PYMS Construction - Pedestrian Bridge - Decking Installation 2021-04-14

    Pedestrian Bridge Decking Installation


    All prior construction updates can be found in the Construction Updates Archive.


    April 8, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: No activity  

    • Timeframe: On hold

     

    North Pavilion  
    Activity: Wall and slab on grade pours; setting of Mezzanine-level rebar

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Production pile driving


    Station Headhouse

    Activity: Mezzanine Level: Preparation of roof slabs

    • Timeframe: Ongoing


    Activity: Platform Level: Pouring platform level walls; installation of roof shoring

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit in crawlspace, CMU walls, and ceiling insulation

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Between platforms: No activity 

    • Timeframe: TBD

    Activity: East and West Platforms: Installation of corridor hangers, racks, conduits, and curbs 

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing 


    Pedestrian Bridge/Knuckle Pier


    Activity: Installation of bridge decking and under-deck conduit

    • Timeframe: Ongoing


    2601 Main Line Blvd.
    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    Construction Gallery

    View A Collection of Photos Illustrating one Year of Construction


    The following are photos from construction of the Potomac Yard Metrorail Station:

    PYMS Construction - North Pavilion Looking East 2021.03.30

    North Pavilion, Looking West


    PYMS Construction - Pedestrian Bridge Looking East 2021.03.30

    Pedestrian Bridge, Looking East


    PYMS Construction - Station Headhouse Looking North 2021.03.30

    Station Headhouse, Looking North


    PYMS Construction - Station Platform, Looking South

    Station Platform, Looking South


    PYMS Construction - AC Switchgear Building 2021.03.30

    A.C. Switchgear Building


    All prior construction updates can be found in the Construction Updates Archive.


    Project Schedule

    PYMS Construction - Construction Schedule 2021.03.22

    Current as of March 22, 2021


    March 2021

    Construction Activity Alerts

    Overnight Construction of Pedestrian Bridge

    A noise variance has been issued to Potomac Yard Constructors for overnight construction to erect the pedestrian bridge over CSX rail tracks. This work is required to take place at night due to CSX regulations regarding work over the active roadway. Note, the work may not be continuous due to weather and availability of CSX work windows.

    Start Dates: March 29, 2021
    End Date: April 26, 2021
    Work Hours: 6 PM - 7 AM (Sunday - Saturday)

    What Residents Can Expect: Crane, light tower, and boom lift noise throughout the night. PYC will insure the light towers and boom lifts are in place during daytime hours to minimize the noise and equipment alarms during nighttime hours. Without compromising a safe working environment, the light towers will be pointed away from residents’ homes as much as practicable.

    For more information, please see Potomac Yard Metrorail Station Noise Variances.


    Pile Driving to Begin at South Pavilion

    Potomac Yard Constructors (PYC) will be driving piles for the Potomac Yard Metrorail Station South Pavilion east the E. Glebe Rd. and Potomac Ave. intersection.

    Start Date: March 15, 2021
    Duration: Approximately 3 weeks, weather permitting
    Work Hours: 9 AM - 6 PM (Monday - Friday); 10 AM - 4 PM (Saturday) 


    Construction News

    View A Collection of Photos Illustrating one Year of Construction


    MARCH 25, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: No activity  

    • Timeframe: On hold

     

    North Pavilion  
    Activity: Installation of vapor barrier and slab on grade pour

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Test and production pile driving


    Station Headhouse

    Activity: Mezzanine Level: Installation of roof rebar

    • Timeframe: Ongoing


    Activity: Platform Level: Pouring platform level walls

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of conduit, CMU walls, and ceiling anchors

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Between platforms: Installation of waterproofing and drainage system 

    • Timeframe: Ongoing

    Activity: East and West Platforms: Installation of corridor hangers, racks, conduits, and curbs 

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation and installation of communication, ATC, and TP duct banks

    • Timeframe: Ongoing 


    Pedestrian Bridge/Knuckle Pier


    Activity: Install bridge planking; installation of anchor bolts on pedestrian bridge

    • Timeframe: Ongoing


    Activity: Erection of bridge trusses over WMATA tracks

    • Timeframe: Ongoing


    2601 Main Line Blvd.
    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    MARCH 18, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: No activity

    • Timeframe: On hold

     

    North Pavilion  
    Activity: Installation of vapor barrier and slab on grade pour.

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Test and production pile driving


    Station Headhouse
    Activity: Platform Level: Pouring platform level walls

    • Timeframe: Ongoing

    Activity: Basement Level: Installation of escalator support columns, CMU walls, and ceiling anchors

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: Between platforms: Backfilling, grading, and waterproofing 

    • Timeframe: Ongoing

    Activity: East and West Platforms: Platform steel erection, installation of hangers, racks, and conduits

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation for communication, ATC, and TP duct banks

    • Timeframe: Ongoing

    Activity: Installation of communications duct manhole

    • Timeframe: Ongoing


    Pedestrian Bridge/Knuckle Pier
    Activity: Assembly and erection of bridge over CSX rail corridor; installation of anchor bolts


    2601 Main Line Blvd.
    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    MARCH 11, 2021 UPDATE

    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Installation of equipment pads, underdrains and waterproofing (west side)

    • Timeframe: Ongoing

     

    North Pavilion  
    Activity: Frost wall pours and back-filling, column encasements, waterproofing

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Test and production piles

    • Timeframe: Mid-March - Late April


    Station Headhouse
    Activity: Waterproofing installation and pouring platform-level walls

    • Timeframe: Ongoing

    Activity: Service-level Plumbing, HVAC, and Electrical Installation

    • Timeframe: Ongoing

    Activity: Station steel erection

    • Timeframe: Ongoing


    Station Platform

    Activity: East Platform: Installation of hangers, racks, and conduits

    • Timeframe: Ongoing

    Activity: East and West Platforms: Platform steel erection and curb installation

    • Timeframe: Ongoing


    Duct Banks

    Activity: Excavation for communication, ATC, and TP duct banks

    • Timeframe: Ongoing

    Activity: Installation of communications duct manhole

    • Timeframe: Ongoing

    Pedestrian Bridge/Knuckle Pier
    Activity: Assembly and erection of bridge over CSX rail corridor

     

    2601 Main Line Blvd.
    Activity: Worker van service to/from construction site

    • Timeframe: Ongoing

    Activity: Construction material staging

    • Timeframe: Ongoing


    March 4, 2021 Update

    **AFTER-HOURS CONSTRUCTION ACTIVITY ALERT**
    A noise variance has been issued to Potomac Yard Constructors for overnight construction to erect the pedestrian bridge over CSX rail tracks. This work is required to take place at night due to CSX regulations regarding work over the active roadway. Note, the work may not be continuous due to weather and availability of CSX work windows.

    Dates: February 17 - March 29, 2021

    Work Hours: 6 PM - 7 AM

    What Residents Can Expect: Crane, light tower, and boom lift noise throughout the night. PYC will insure the light towers and boom lifts are in place during daytime hours to minimize the noise and equipment alarms during nighttime hours. Without compromising a safe working environment, the light towers will be pointed away from residents’ homes as much as practicable.

    For more information, please see Potomac Yard Metrorail Station Noise Variances.


    Construction Work

    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

    AC Switchgear Building
    Activity: Installation of equipment pads, interior CMU and brick veneer

    • Timeframe: Ongoing

     

    North Pavilion  
    Activity: Frost wall pours and back-filling, column encasements, slab-on-grade pour

    • Timeframe: Ongoing


    South Pavilion  

    Activity: Test and production piles

    • Timeframe: Early March


    Station Headhouse
    Activity: Headhouse: Forming mezzanine level roof, curbs and walls; installation of service level conduit

    • Timeframe: Ongoing

      Activity: Station steel erections

      • Timeframe: Ongoing


      Station Platform

      Activity: East Platform: Installation remaining decks

      • Timeframe: Ongoing


      Activity: West Platform: Curing of deck

      • Timeframe: Ongoing


      Activity: Platforms: Waterproofing platform foundation

      • Timeframe: Ongoing


      Activity: Between Platforms: Dewatering and waterproofing

      • Timeframe: Ongoing

      Duct Banks

        Activity: Excavation for communication, ATC, and TP duct banks

        • Timeframe: Ongoing

        Activity: Installation of communications duct manhole

        • Timeframe: Ongoing

        Pedestrian Bridge/Knuckle Pier
        Activity: Erection of bridge over CSX rail corridor

         

        2601 Main Line Blvd.
        Activity: Worker van service to/from construction site

        • Timeframe: Ongoing

        Activity: Construction material staging

        • Timeframe: Ongoing



        February 2021

        February 25, 2021 Update

        **AFTER-HOURS CONSTRUCTION ACTIVITY ALERT**
        A noise variance has been issued to Potomac Yard Constructors for overnight construction to erect the pedestrian bridge over CSX rail tracks. This work is required to take place at night due to CSX regulations regarding work over the active roadway. Note, the work may not be continuous due to weather and availability of CSX work windows.

        Dates: February 17 - March 6, 2021

        Work Hours: 6 PM - 7 AM

        What Residents Can Expect: Crane, light tower, and boom lift noise throughout the night. PYC will insure the light towers and boom lifts are in place during daytime hours to minimize the noise and equipment alarms during nighttime hours. Without compromising a safe working environment, the light towers will be pointed away from residents’ homes as much as practicable.

        For more information, please see Potomac Yard Metrorail Station Noise Variances.


        Construction Work

        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

        AC Switchgear Building
        Activity: Installation of equipment pads, interior CMU and brick veneer

        • Timeframe: Through mid-March

         

        North Pavilion  
        Activity: Completion of frost wall formation, column encasements, and slab-on-grade pour

        • Timeframe: Ongoing


        South Pavilion
        Activity: Construction of access ramp

        • Timeframe: Ongoing 

        Activity: Excavation for pier foundations

        • Timeframe: Ongoing

        Activity: Test piles

        • Timeframe: Beginning of March


        Station Headhouse
        Activity: Headhouse: Forming mezzanine level roof, curbs and walls; installation of service level conduit

        • Timeframe: Ongoing

          Activity: Station steel erections

          • Timeframe: Beginning late February


          Station Platform

          Activity: East Platform: Installation remaining decks

          • Timeframe: Through the end of February


          Activity: West Platform: Installation of remaining decks

          • Timeframe: Through the end of February


          Duct Banks

            Activity: Completing ties to cross-overs

            • Timeframe: Ongoing

            Activity: Stub-up pours

            • Timeframe: Ongoing

            Pedestrian Bridge/Knuckle Pier
            Activity: Erection of bridge over CSX rail corridor

             

            2601 Main Line Blvd.
            Activity: Worker van service to/from construction site

            • Timeframe: Ongoing

            Activity: Construction material staging

            • Timeframe: Ongoing


            Construction Gallery

            The following are photos from the erection of the pedestrian bridge over CSX railroad tracks:

              PYMS Construction - Truss Over CSX Track 1 2021.02.25

            PYMS Construction - Truss Over CSX Track 2 2021.02.25

            PYMS Construction - Truss Over CSX Track 3 2021.02.25

            PYMS Construction - Truss Over CSX Track 4 2021.02.25

            February 18, 2021 Update

            Construction Work

            The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

            AC Switchgear Building
            Activity: Installation of equipment pads, interior CMU and brick veneer

            • Timeframe: Through mid-March

             

            North Pavilion  
            Activity: Completion of frost wall formation, column encasements, and slab-on-grade pour

            • Timeframe: Ongoing


            South Pavilion
            Activity: Construction of access ramp

            • Timeframe: Ongoing 

            Activity: Excavation for pier foundations

            • Timeframe: Ongoing

            Activity: Test piles

            • Timeframe: Beginning end of February


            Station Headhouse
            Activity: East Headhouse: Forming mezzanine level roof, curbs and walls; installation of service level conduit

            • Timeframe: Ongoing

            Activity: West Headhouse: Forming mezzanine level roof slab and walls

            • Timeframe: Ongoing

            Activity: Station steel erections

            • Timeframe: Beginning late February


            Station Platform

            Activity: East Platform: Installation remaining decks

            • Timeframe: Through the end of February


            Activity: West Platform: Installation of remaining decks

            • Timeframe: Through the end of February


            Duct Banks

              Activity: Forming and pouring of concrete duct banks

              • Timeframe: Ongoing


              Knuckle Pier
              Activity: Preparation for pedestrian bridge frame erection over the rail corridor

              • Timeframe: Late February/Early March
              • *Erection of pedestrian bridge will be conducted during night hours. A noise variance has been issued for this work. 
               

              2601 Main Line Blvd.
              Activity: Worker van service to/from construction site

              • Timeframe: Ongoing

              Activity: Construction material staging

              • Timeframe: Ongoing


              Construction Gallery

              The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

               

                PYMS Construction - Shoring Towers and Bridge Steel 2021.02.11

              Photo of preparations for erection of the pedestrian bridge: shoring towers and bridge steel at the Potomac Yard Metro Station taken on February 11, 2021


              PYMS Construction - Shoring Towers and Bridge Steel 2 2021.02.11

              Photo of preparations for erection of the pedestrian bridge: shoring towers and bridge steel at the Potomac Yard Metro Station taken on February 11, 2021


              February 11, 2021 Update

              Construction Work

              The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

              AC Switchgear Building
              Activity: Installation of interior CMU and brick veneer 
              • Timeframe: Through mid-March

               

              North Pavilion  

              Activity: Completion of frost wall formation, waterproofing, and backfilling

              • Timeframe: Ongoing           


              South Pavilion
              Activity: Construction of access ramp

              • Timeframe: Ongoing 

              Activity: Excavation for piers

              • Timeframe: Ongoing
                 

              Station Headhouse
              Activity: East Headhouse: Forming mezzanine level roof, curbs and walls; installation of service level conduit

              • Timeframe: Ongoing

              Activity: West Headhouse: Forming mezzanine level walls; installation of rebar for mezzanine level roof; removal of shoring

              • Timeframe: Ongoing


              Station Platform  

              Activity: East Platform: Installation of service level conduits

              • Timeframe: Ongoing


              Activity: West Platform: Installation of rebar for stone corbels; formation of stone corbels; waterproofing

              • Timeframe: Through the end of February


              Duct Banks

                Activity: Forming and pouring of concrete duct banks

                • Timeframe: Ongoing


                Knuckle Pier
                Activity: Preparation for pedestrian bridge frame erection over the rail corridor

                • Timeframe: Through mid-February
                 

                2601 Main Line Blvd.
                Activity: Worker van service to/from construction site

                • Timeframe: Ongoing

                Activity: Construction material staging

                • Timeframe: Ongoing


                Construction Gallery

                The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                 

                  PYMS Construction - Shoring Towers and Bridge Steel 2021.02.11

                Photo of preparations for erection of the pedestrian bridge: shoring towers and bridge steel at the Potomac Yard Metro Station taken on February 11, 2021


                PYMS Construction - Shoring Towers and Bridge Steel 2 2021.02.11

                Photo of preparations for erection of the pedestrian bridge: shoring towers and bridge steel at the Potomac Yard Metro Station taken on February 11, 2021


                February 4, 2021 Update

                Construction Work

                The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                AC Switchgear Building
                Activity: Preparation for floor and equipment slab pours 
                • Timeframe: Throughout February

                 

                North Pavilion  

                Activity: Completion of frost wall formation, waterproofing, and backfilling

                • Timeframe: Ongoing           


                South Pavilion
                Activity: Construction of access ramp

                • Timeframe: Ongoing 

                Activity: Excavation for piers

                • Timeframe: Ongoing
                   

                Station Headhouse
                Activity: East Headhouse: Forming mezzanine level roof, curbs and walls; installation of service level conduit

                • Timeframe: Ongoing

                Activity: West Headhouse: Forming mezzanine level walls; installation of rebar for mezzanine level roof; removal of shoring

                • Timeframe: Ongoing


                Station Platform  

                Activity: East Platform: Installation of service level conduits

                • Timeframe: Ongoing


                Activity: West Platform: Installation of rebar for stone corbels; formation of stone corbels; waterproofing

                • Timeframe: Through end of February


                Duct Banks

                  Activity: Forming and pouring of concrete duct banks

                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Installation of anchor bolts; concrete rub and patch process

                  • Timeframe: Ongoing
                   

                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                   

                  PYMS Construction - Bridge Steel 2021.02.04

                  Photo of bridge steel for the Potomac Yard Metro Station taken on February 4, 2021


                  PYMS Construction - Duct Bank Installation 2021.02.04

                  Photo taken on February 4, 2021, of the duct bank being installed during construction of the Potomac Yard Metro Station


                  PYMS Construction - South Pavilion Site Fencing  2021.02.04

                  Photo of South Pavilion site fencing along Potomac Ave. taken on February 4, 2021


                  PYMS Construction - North Pavilion Frost Walls 2021.02.04

                  Photo of the North Pavilion frost walls taken on February 4, 2021


                  PYMS Construction - Knuckle Pier Looking West 2021.02.04

                  Photo of the Platform and Knuckle Pier taken on February 4, 2021


                  PYMS Construction - North Pavilion 2021.02.04

                  Photo of the North Pavilion taken on February 4, 2021


                  PYMS Construction - South Pavilion Shoring Tower and Bridge Steel 2021.02.04

                  Photo of the shoring tower and bridge steel taken on February 4, 2021


                  January 2021

                  January 28, 2021 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Preparation for floor and equipment slab pours 
                  • Timeframe: February

                   

                  North Pavilion
                  Activity: Continuing metal deck installation for mezzanine and roof slabs

                  • Timeframe: Ongoing             
                                  

                  Activity: Completion of formation and pouring of frost walls 

                  • Timeframe: Ongoing           


                  South Pavilion
                  Activity: Installation of erosion and sediment control 

                  • Timeframe: Ongoing 
                     

                  Activity: Installation of perimeter fence

                  • Timeframe: Ongoing

                  Activity: Excavation for piers

                  • Timeframe: Ongoing
                     

                  Station Headhouse and Platform  
                  Activity: East Headhouse Mezzanine: Shoring removal

                  • Timeframe: Ongoing

                  Activity: West Headhouse Mezzanine: Installation of rebar for mezzanine level walls

                  • Timeframe: Ongoing

                  Activity: Platforms: Pouring of corbel stone and overhang

                  • Timeframe: Ongoing

                  Activity: Installation of duct banks

                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Preparations for bridge placement

                  • Timeframe: Ongoing


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - Headhouse Looking South 2021.01.19

                  View of the Metro platforms, looking south


                  PYMS Construction - Headhouse Rebar Installation 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - Headhouse Rebar Installation 4 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - Headhouse Rebar Installation 3 2021.01.19

                  View of Mezzanine floor slab rebar

                   

                  PYMS Construction - Headhouse Rebar Installation 2 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - North Pavillion Looking East 2021.01.19

                  View of North Pavilion structural steel - looking east


                  PYMS Construction - North Pavillion Looking Northwest 2021.01.19

                  View of North Pavilion structural steel - looking west


                  January 22, 2021 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Preparation for floor slab pour
                  • Timeframe: Late January

                   

                  North Pavilion
                  Activity: Begin metal deck installation for mezzanine and roof slabs

                  • Timeframe: Through end of January      
                                  

                  Activity: Form frost walls

                  • Timeframe: Through beginning of February              


                  South Pavilion
                  Activity: Installation of erosion and sediment control 

                  • Timeframe: Ongoing 
                     

                  Activity: Installation of perimeter fence; clearing and grubbing

                  • Timeframe: Ongoing

                  Activity: Removal of median nose at intersection of Seaton Avenue and Potomac Avenue

                  • Timeframe: Through end of January
                  • Approved MOT for pedestrian and bicycle traffic


                  Station Headhouse and Platform  
                  Activity: East Headhouse Mezzanine: Mezzanine floor slab pour; installation of slab electrical and drainage work

                  • Timeframe: Ongoing

                  Activity: West Headhouse Mezzanine: Pouring of bridge abutment wall; installation mezzanine slab shoring tower

                  • Timeframe: Ongoing

                  Activity: Platforms: Pouring of corbel stone and overhang

                  • Timeframe: Ongoing

                  Activity: Installation of duct banks

                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Parging of the Knuckle Pier

                  • Timeframe: Ongoing


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - Headhouse Looking South 2021.01.19

                  View of the Metro platforms, looking south


                  PYMS Construction - Headhouse Rebar Installation 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - Headhouse Rebar Installation 4 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - Headhouse Rebar Installation 3 2021.01.19

                  View of Mezzanine floor slab rebar

                   

                  PYMS Construction - Headhouse Rebar Installation 2 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - North Pavillion Looking East 2021.01.19

                  View of North Pavilion structural steel - looking east


                  PYMS Construction - North Pavillion Looking Northwest 2021.01.19

                  View of North Pavilion structural steel - looking west


                  All prior construction updates can be found in the Construction Updates Archive.


                  January 11, 2021 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Pouring drainage pits, floor slabs, and equipment slabs
                  • Timeframe: Through end of January

                   

                  North Pavilion
                  Activity: Complete structural steel

                  • Timeframe: Through end of January      
                                  

                  Activity: Form frost walls

                  • Timeframe: Through beginning of February              


                  South Pavilion
                  Activity: Installation of erosion and sediment control 

                  • Timeframe: Ongoing 

                  Activity: Installation of perimeter fence; clearing and grubbing

                  • Timeframe: Ongoing

                  Activity: Removal of median nose at intersection of Seaton Avenue and Potomac Avenue

                  • Timeframe: Through end of January
                  • Approved MOT for pedestrian and bicycle traffic


                  Station Headhouse and Platform  
                  Activity: East Headhouse Mezzanine: Mezzanine floor slab pour; installation of slab electrical and drainage work

                  • Timeframe: Ongoing

                  Activity: West Headhouse Mezzanine: Pouring of bridge abutment wall; installation mezzanine slab shoring tower

                  • Timeframe: Ongoing

                  Activity: Platforms: Pouring of corbel stone and overhang

                  • Timeframe: Ongoing

                  Activity: Installation of duct banks

                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Stripping of knuckle beams

                  • Timeframe: Ongoing


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - Headhouse Looking South 2021.01.19

                  View of the Metro platforms, looking south


                  PYMS Construction - Headhouse Rebar Installation 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - Headhouse Rebar Installation 4 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - Headhouse Rebar Installation 3 2021.01.19

                  View of Mezzanine floor slab rebar

                   

                  PYMS Construction - Headhouse Rebar Installation 2 2021.01.19

                  View of Mezzanine floor slab rebar


                  PYMS Construction - North Pavillion Looking East 2021.01.19

                  View of North Pavilion structural steel - looking east


                  PYMS Construction - North Pavillion Looking Northwest 2021.01.19

                  View of North Pavilion structural steel - looking west


                  All prior construction updates can be found in the Construction Updates Archive.


                  Project Schedule

                  Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                  Current as of June 29, 2020


                  December 2020

                  December 16, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Installation of steel erection and decking; pouring of roof slab
                  • Timeframe: Through end of December

                  Activity: Installation of under-slab plumbing

                  • Timeframe: Through end of December


                  North Pavilion
                  Activity: Back-filling frost walls and around grade beams

                  • Timeframe: Through end of December 
                                  

                  Activity: Structural steel deliveries

                  • Timeframe: Ongoing              


                  South Pavilion
                  Activity: Relocation of CSX fence

                  • Timeframe: Through end of December


                  Activity: Clearing and Grubbing

                  • Timeframe: Through mid-January


                  Station Headhouse and Platform  
                  Activity: East Headhouse Mezzanine: Installation of shoring towers and slab rebar

                  • Timeframe: Ongoing

                  Activity: West Headhouse Mezzanine: Installation of shoring towers and slab rebar

                  • Timeframe: Ongoing

                  Activity: East Platform: Installation of the decking forms

                  • Timeframe: Ongoing

                  Activity: Installation of duct banks

                  • Timeframe: Through end of December


                  Knuckle Pier
                  Activity: Formation of knuckle beams

                  • Timeframe: Through end of December

                  Activity: Installation of pier cap rebar

                  • Timeframe: Through end of December


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - 2020.10.16 Update 1

                  PYMS Construction - 2020.10.16 Update 2

                  PYMS Construction - 2020.10.16 Update 3

                   

                  All prior construction updates can be found in the Construction Updates Archive.


                  December 10, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Installation of steel erection and decking; pouring of roof slab
                  • Timeframe: Through end of December

                  Activity: Installation of under-slab plumbing and pouring of floor slab

                  • Timeframe: Through end of December


                  North Pavilion
                  Activity: Back-filling frost walls and around grade beams

                  • Timeframe: Through end of December                


                  South Pavilion
                  Activity: Relocation of CSX fence

                  • Timeframe: Through end of December


                  Station Headhouse and Platform  
                  Activity: East Headhouse Mezzanine: Install shoring towers and slab rebar

                  • Timeframe: Ongoing

                  Activity: West Headhouse Mezzanine: Install shoring towers

                  • Timeframe: Ongoing

                  Activity: East Platform: Installation of the decking forms and reinforcing

                  • Timeframe: Ongoing

                  Activity: Installation of duct banks

                  • Timeframe: Through mid-December


                  Knuckle Pier
                  Activity: Formation of knuckle beams

                  • Timeframe: Through mid-December

                  Activity: Installation of knuckle cap rebar

                  • Timeframe: Through mid-December


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  December 2, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Steel erection and pouring of roof slab
                  • Timeframe: Through mid-December

                  Activity: Installation of under-slab plumbing and pouring of floor slab

                  • Timeframe: Through mid-December


                  North Pavilion
                  Activity: Stripping forms and back-filling

                  • Timeframe: Through mid-December                


                  South Pavilion
                  Activity: Relocation of CSX fence

                  • Timeframe: Anticipated to start second week of December


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse walls, platform decks, and mezzanine columns

                  • Timeframe: Ongoing

                  Activity: Forming of elevator pit slabs

                  • Timeframe: Ongoing

                  Activity: Formation and pouring of bridge abutment walls at west headhouse platform

                  • Timeframe: Ongoing

                  Activity: Install duct banks (north and south)

                  • Timeframe: Through mid-December


                  Knuckle Pier
                  Activity: No activity

                  • Timeframe: Through mid-December


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  November 2020

                  November 19, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Steel erection ongoing for floors and roof deck and pour roof slab
                  • Timeframe: Through mid-December

                  Activity: Install under-slab plumbing 

                  • Timeframe: End of November

                  North Pavilion
                  Activity: Pouring of column buttresses, elevator, and escalator pit walls

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: No activity

                  • Timeframe: N/A


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse walls, platform decks, and mezzanine columns

                  • Timeframe: Ongoing

                  Activity: Forming of elevator pit slabs

                  • Timeframe: Ongoing


                  Activity: Formation and pouring of bridge abutment walls at west headhouse platform

                  • Timeframe: Ongoing through early December


                  Activity: Install duct banks (north and south)

                  • Timeframe: Ongoing through early December


                  Activity: Grading between station platforms
                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: No activity

                  • Timeframe: Through end of November


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging
                  • Timeframe: Ongoing


                  November 12, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Steel erection ongoing for floors and roof deck
                  • Timeframe: End of November


                  North Pavilion
                  Activity: Pouring of column buttresses, elevator, and escalator pit walls

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: No activity

                  • Timeframe: N/A


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse walls, platform decks, and mezzanine columns

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing through early December

                  Activity: Grading between station headhouse and existing WMATA tracks
                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Forming beams and bearing pads

                  • Timeframe: End of November


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging
                  • Timeframe: Ongoing


                  November 5, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Steel erection ongoing for floors and roof deck
                  • Timeframe: November


                  North Pavilion
                  Activity: Pouring of column buttresses, elevator, and escalator pit walls

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: No activity

                  • Timeframe: N/A


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse walls, platform decks, and columns

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing through early December

                  Activity: Grading between station headhouse and existing WMATA tracks

                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Forming beams and bearing pads

                  • Timeframe: Through mid-November


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  October 2020

                  October 29, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Stripping wall forms and erecting steel for roof trusses
                  • Timeframe: Through mid-November


                  North Pavilion
                  Activity: Pouring of column buttresses, elevator, and escalator pits

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: No activity

                  • Timeframe: N/A


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse walls, platform decks, and columns

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing

                  Activity: Grading between station headhouse and existing WMATA tracks

                  • Timeframe: Ongoing


                  Knuckle Pier
                  Activity: Forming beams and pedestals

                  • Timeframe: Through mid-November


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  **Before-Hours Construction Activity Alert**

                  Potomac Yard Constructors (PYC) has been issued a noise variance permit for before-hours construction. Workers will be placing concrete for the station structure. Early access via the Carpenter Drive site entrance is required due to the size of the placements and the time necessary for concrete finishing.

                  • Dates: September 9 – October 31, 2020
                  • Days of the week: Monday – Friday, not including holidays
                  • Hours Permitted: 5 – 7 AM
                  • Location: Carpenter Drive site entrance.
                  • What Residents Can Expect: Trucks will be arriving on site early. The gate will be open to prevent the idling or staging of trucks adjacent to residences. Truck drivers will be directed to proceed directly into the site down and continue to north end of the project away from the residences.  Light towers may be required. If so, the Contractor will ensure the towers are pointed away from residents’ homes as much as possible.
                  • Contact Information:
                    • On-site contact: Matt Prpich with PYC, 201.713.6429 (available during early hours construction)
                    • City Inspector: Brian Whiteley, Department of Project Implementation, 703.656.6025 (available during regular City business hours)

                  Read the letter distributed to residents about this activity.

                  Learn more about Potomac Yard Metrorail Station project construction noise variances.



                  October 16, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Forming and pouring walls
                  • Timeframe: Through October


                  North Pavilion
                  Activity: Installation of grade beam caps, pit slabs, and column buttresses

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: Site survey work

                  • Timeframe: Ongoing


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing

                     

                  Knuckle Pier
                  Activity: Beam pours

                  • Timeframe: Late October


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - 2020.10.16 Update 1

                  PYMS Construction - 2020.10.16 Update 2

                  PYMS Construction - 2020.10.16 Update 3

                   

                  All prior construction updates can be found in the Construction Updates Archive.


                  Project Schedule

                  Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                  Current as of June 29, 2020


                  **Before-Hours Construction Activity Alert**

                  Potomac Yard Constructors (PYC) has been issued a noise variance permit for before-hours construction. Workers will be placing concrete for the station structure. Early access via the Carpenter Drive site entrance is required due to the size of the placements and the time necessary for concrete finishing.

                  • Dates: September 9 – October 31, 2020
                  • Days of the week: Monday – Friday, not including holidays
                  • Hours Permitted: 5 – 7 AM
                  • Location: Carpenter Drive site entrance.
                  • What Residents Can Expect: Trucks will be arriving on site early. The gate will be open to prevent the idling or staging of trucks adjacent to residences. Truck drivers will be directed to proceed directly into the site down and continue to north end of the project away from the residences.  Light towers may be required. If so, the Contractor will ensure the towers are pointed away from residents’ homes as much as possible.
                  • Contact Information:
                    • On-site contact: Matt Prpich with PYC, 201.713.6429 (available during early hours construction)
                    • City Inspector: Brian Whiteley, Department of Project Implementation, 703.656.6025 (available during regular City business hours)

                  Read the letter distributed to residents about this activity.

                  Learn more about Potomac Yard Metrorail Station project construction noise variances.



                  October 7, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Forming and pouring walls
                  • Timeframe: Through mid-late October


                  North Pavilion
                  Activity: Installation of grade beam caps, pit slabs, and column buttresses

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: Site survey work

                  • Timeframe: Ongoing


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing

                     

                  Knuckle Pier
                  Activity: No activity

                  • Timeframe: N/A


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - Foundation Formwork 2020.09.10

                  North Pavilion Foundation Formwork


                  PYMS Construction - North Pavilion Looking Southeast 2020.09.23

                  North Pavilion Looking Towards the Knuckle Pier         


                  PYMS Construction - North Pavilion from the Knuckle 2020.09.18

                  North Pavilion from the Knuckle Pier


                  PYMS Construction - Station Site from the Knuckle Pier 2020.09.23

                  Station Site from the Knuckle Pier


                  PYMS Construction - Station Headhouse Looking South

                  Looking South from the Station Headhouse


                  All prior construction updates can be found in the Construction Updates Archive.


                  Project Schedule

                  Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                  Current as of June 29, 2020


                  September 2020

                  **Before-Hours Construction Activity Alert**

                  Potomac Yard Constructors (PYC) has been issued a noise variance permit for before-hours construction. Workers will be placing concrete for the station structure. Early access via the Carpenter Drive site entrance is required due to the size of the placements and the time necessary for concrete finishing.

                  • Dates: September 9 – October 31, 2020
                  • Days of the week: Monday – Friday, not including holidays
                  • Hours Permitted: 5 – 7 AM
                  • Location: Carpenter Drive site entrance.
                  • What Residents Can Expect: Trucks will be arriving on site early. The gate will be open to prevent the idling or staging of trucks adjacent to residences. Truck drivers will be directed to proceed directly into the site down and continue to north end of the project away from the residences.  Light towers may be required. If so, the Contractor will ensure the towers are pointed away from residents’ homes as much as possible.
                  • Contact Information:
                    • On-site contact: Matt Prpich with PYC, 201.713.6429 (available during early hours construction)
                    • City Inspector: Brian Whiteley, Department of Project Implementation, 703.656.6025 (available during regular City business hours)

                  Read the letter distributed to residents about this activity.

                  Learn more about Potomac Yard Metrorail Station project construction noise variances.



                  September 23, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Forming and pouring walls
                  • Timeframe: Through early October


                  North Pavilion
                  Activity: Installation of grade beam caps and pit slabs

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: Site survey work

                  • Timeframe: Ongoing


                  Station Headhouse, Platform and Mezzanine  
                  Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing

                     

                  Knuckle Pier
                  Activity: Formwork for the top beam

                  • Timeframe: Ongoing


                  2601 Main Line Blvd.
                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing


                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - Foundation Formwork 2020.09.10

                  North Pavilion Foundation Formwork


                  PYMS Construction - North Pavilion Looking Southeast 2020.09.23

                  North Pavilion Looking Towards the Knuckle Pier         


                  PYMS Construction - North Pavilion from the Knuckle 2020.09.18

                  North Pavilion from the Knuckle Pier


                  PYMS Construction - Station Site from the Knuckle Pier 2020.09.23

                  Station Site from the Knuckle Pier


                  PYMS Construction - Station Headhouse Looking South

                  Looking South from the Station Headhouse


                  All prior construction updates can be found in the Construction Updates Archive.


                  Project Schedule

                  Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                  Current as of June 29, 2020

                  September 17, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Forming walls
                  • Timeframe: Through early October


                  North Pavilion

                  Activity: Installation of grade beam caps

                  • Timeframe: Ongoing           



                  South Pavilion

                  Activity: Site survey work

                  • Timeframe: Ongoing


                  Station Headhouse, Platform and Mezzanine  

                  Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing

                     

                  Knuckle Pier

                  Activity: Formwork for the top beam

                  • Timeframe: Ongoing


                  2601 Main Line Blvd.

                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing
                  • Duration: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing

                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - Duct Bank 2020.09.17

                  Duct Banks


                  PYMS Construction - West Headhouse Foundation Slab

                  Pouring of Concrete for the West Headhouse Foundation Slab       

                                

                  PYMS Construction - West Headhouse Foundation Slab Exterior

                  West Headhouse Foundation Slab


                  PYMS Construction - Knuckle Pier

                  Knuckle Pier


                  All prior construction updates can be found in the Construction Updates Archive.


                  Project Schedule

                  Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                  Current as of June 29, 2020


                  **Before-Hours COnstruction Activity Alert**

                  Potomac Yard Constructors (PYC) has been issued a noise variance permit for before-hours construction. Workers will be placing concrete for the station structure. Early access via the Carpenter Drive site entrance is required due to the size of the placements and the time necessary for concrete finishing.

                  • Dates: September 9 – October 31, 2020
                  • Days of the week: Monday – Friday, not including holidays
                  • Hours Permitted: 5 – 7 AM
                  • Location: Carpenter Drive site entrance.
                  • What Residents Can Expect: Trucks will be arriving on site early. The gate will be open to prevent the idling or staging of trucks adjacent to residences. Truck drivers will be directed to proceed directly into the site down and continue to north end of the project away from the residences.  Light towers may be required. If so, the Contractor will ensure the towers are pointed away from residents’ homes as much as possible.
                  • Contact Information:
                    • On-site contact: Matt Prpich with PYC, 201.713.6429 (available during early hours construction)
                    • City Inspector: Brian Whiteley, Department of Project Implementation, 703.656.6025 (available during regular City business hours)

                  Read the letter distributed to residents about this activity.

                  See additional information about noise variances issued for the project.


                  September 9, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Forming walls

                  • Timeframe: Through early October


                  North Pavilion

                  Activity: Installation of grade beam caps

                  • Timeframe: Ongoing           

                  Activity: Pouring elevator and escalator pits

                  • Timeframe: Through the end of September           

                  South Pavilion

                  Activity: Site survey work

                  • Timeframe: Ongoing


                  Station Headhouse, Platform and Mezzanine  

                  Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                  • Timeframe: Ongoing

                  Activity: Installation of duct bank

                  • Timeframe: Ongoing


                  Activity: Grading and installation of Load Transfer Platform (LTP)

                  • Timeframe: Ongoing

                  Activity: Site fill operations

                  • Timeframe: Ongoing
                  • Notes: PYC will bring in clean fill from a quarry

                   

                  2601 Main Line Blvd.

                  Activity: Worker van service to/from construction site

                  • Timeframe: Ongoing
                  • Duration: Ongoing

                  Activity: Construction material staging

                  • Timeframe: Ongoing

                  Construction Gallery

                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                  PYMS Construction - East Side of Headhouse 2020.08.06

                  Construction activity on the east side of the station headhouse.


                  PYMS Construction - East Side Looking South 2020.08.06

                  Construction activity on the east side of the station headhouse while looking south


                  PYMS Construction - Rebar installation at station headhouse 2020.08.06

                  Installation of rebar for the station headhouse


                  PYMS Construction - AC Switchgear West Wall 2020.08.06

                  Construction of the AC Switchgear Building west wall


                  All prior construction updates can be found in the Construction Updates Archive.


                  Project Schedule

                  Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                  Current as of June 29, 2020


                  September 2, 2020 Update

                  Construction Work

                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                  AC Switchgear Building
                  Activity: Forming north and east walls

                  • Timeframe: Through end of September


                  North Pavilion

                  Activity: Installation of grade beam caps

                  • Timeframe: Ongoing           


                  South Pavilion

                  Activity: Site survey work

                  • Timeframe: Ongoing


                  Station Headhouse, Platform and Mezzanine  

                  Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                  • Timeframe: Ongoing

                    Activity: Installation of duct bank

                    • Timeframe: Ongoing


                    Activity: Grading and installation of Load Transfer Platform (LTP)

                    • Timeframe: Ongoing

                    Activity: Site fill operations

                    • Timeframe: Ongoing
                    • Notes: PYC will bring in clean fill from a quarry

                     

                    2601 Main Line Blvd.

                    Activity: Worker van service to/from construction site

                    • Timeframe: Ongoing
                    • Duration: Ongoing

                    Activity: Construction material staging

                    • Timeframe: Ongoing

                    Construction Gallery

                    The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                    PYMS Construction - East Side of Headhouse 2020.08.06

                    Construction activity on the east side of the station headhouse.


                    PYMS Construction - East Side Looking South 2020.08.06

                    Construction activity on the east side of the station headhouse while looking south


                    PYMS Construction - Rebar installation at station headhouse 2020.08.06

                    Installation of rebar for the station headhouse


                    PYMS Construction - AC Switchgear West Wall 2020.08.06

                    Construction of the AC Switchgear Building west wall


                    All prior construction updates can be found in the Construction Updates Archive.


                    Project Schedule

                    Potomac Yard Metrorail Station Construction Schedule 2020.09.02

                    Current as of June 29, 2020


                    August 2020

                    August 13, 2020 Update

                    Construction Work

                    The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                    AC Switchgear Building
                    Activity: Demolition of the north and east walls

                    • Timeframe: August 10 - 21
                    • Note: Demolition taking place due to quality concerns regarding wall concrete placement. The contractor is responsible for demolition and rework. 


                    North Pavilion

                    Activity: Installation of grade beam caps

                    • Timeframe: Ongoing           


                    South Pavilion

                    Activity: Site survey work

                    • Timeframe: Ongoing


                    Station Headhouse, Platform and Mezzanine  

                    Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                    • Timeframe: Ongoing

                      Activity: Installation of duct bank

                      • Timeframe: Ongoing


                      Activity: Grading and installation of Load Transfer Platform (LTP)

                      • Timeframe: Ongoing

                      Activity: Site fill operations

                      • Timeframe: Ongoing
                      • Notes: PYC will bring in clean fill from a quarry

                       

                      2601 Main Line Blvd.

                      Activity: Worker van service to/from construction site

                      • Timeframe: Ongoing
                      • Duration: Ongoing


                      Construction Gallery

                      The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                      PYMS Construction - East Side of Headhouse 2020.08.06

                      Construction activity on the east side of the station headhouse.


                      PYMS Construction - East Side Looking South 2020.08.06

                      Construction activity on the east side of the station headhouse while looking south


                      PYMS Construction - Rebar installation at station headhouse 2020.08.06

                      Installation of rebar for the station headhouse


                      PYMS Construction - AC Switchgear West Wall 2020.08.06

                      Construction of the AC Switchgear Building west wall


                      August 6, 2020 Update

                      Construction Work

                      The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                      AC Switchgear Building
                      Activity: Formation and placement of concrete for the building foundation and walls

                      • Timeframe: Ongoing


                      North Pavilion

                      Activity: Foundation work at the "knuckle" pier

                      • Timeframe: Ongoing

                      Activity: Waterproofing of the North Pavilion foundation

                      • Timeframe: Ongoing           


                      South Pavilion

                      Activity: Site survey work

                      • Timeframe: Ongoing


                      Station Headhouse, Platform and Mezzanine  

                      Activity: Formation of headhouse and platform foundation walls,  columns, and slabs

                      • Timeframe: Ongoing

                        Activity: Installation of duct bank

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Notes: PYC will bring in clean fill from a quarry

                         

                        2601 Main Line Blvd.

                        Activity: Worker van service to/from construction site

                        • Timeframe: Ongoing
                        • Duration: Ongoing


                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        PYMS Construction - East Side of Headhouse 2020.08.06

                        Construction activity on the east side of the station headhouse.


                        PYMS Construction - East Side Looking South 2020.08.06

                        Construction activity on the east side of the station headhouse while looking south


                        PYMS Construction - Rebar installation at station headhouse 2020.08.06

                        Installation of rebar for the station headhouse


                        PYMS Construction - AC Switchgear West Wall 2020.08.06

                        Construction of the AC Switchgear Building west wall


                        All prior construction updates can be found in the Construction Updates Archive.


                        July 2020

                        July 16, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Foundation work at the "knuckle" pier

                        • Timeframe: Ongoing

                        Activity: Foundation work on the North Pavilion

                        • Timeframe: Ongoing           


                        South Pavilion

                        Activity: Site survey work

                        • Timeframe: Mid to late July


                        Station Headhouse, Platform and Mezzanine  

                        Activity: Formation of Headhouse foundation walls,  columns, and slabs

                        • Timeframe: Ongoing

                        Activity: Installation of storm drain pipes

                        • Timeframe: Ongoing

                        Activity: Installation of duct bank

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry

                         

                        2601 Main Line Blvd.

                        Activity: Worker van service to/from construction site

                        • Timeframe: Ongoing
                        • Duration: Ongoing


                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        New photos coming soon!


                        June 2020

                        June 30, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Foundation work at the "knuckle" pier

                        • Timeframe: Ongoing

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Station Headhouse, Platform and Mezzanine  

                        Activity: Formation of Headhouse foundation walls,  columns, and slabs

                        • Timeframe: Ongoing

                        Activity: Installation of storm drain pipes

                        • Timeframe: Ongoing

                        Activity: Installation of duct bank

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry

                         

                        2601 Main Line Blvd.

                        Activity: Worker van service to/from construction site begins

                        • Timeframe: Ongoing
                        • Duration: Ongoing


                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        New photos coming soon!


                        All prior construction updates can be found in the Construction Updates Archive.


                        Project Schedule

                        Potomac Yard Metrorail Station Construction Schedule 2020.06.30

                        Current as of June 29, 2020


                        June 25, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Foundation work at the "knuckle" pier

                        • Timeframe: Ongoing

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Station Headhouse, Platform and Mezzanine  

                        Activity: Formation of Headhouse foundation walls,  columns, and slabs

                        • Timeframe: Ongoing

                        Activity: Installation of storm drain pipes

                        • Timeframe: Ongoing

                        Activity: Installation of duct bank

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry

                         

                        2601 Main Line Blvd.

                        Activity: Worker van service to/from construction site begins

                        • Timeframe: Ongoing
                        • Duration: Ongoing


                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        New photos coming soon!


                        All prior construction updates can be found in the Construction Updates Archive.


                        Project Schedule

                        Potomac Yard Metro Station Construction Schedule 2020.04.30

                        Current as of May 29, 2020


                        June 18, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Foundation work at the "knuckle" pier

                        • Timeframe: Ongoing

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Station Headhouse, Platform and Mezzanine  

                        Activity: Formation of foundation walls and columns for Headhouse

                        • Timeframe: Ongoing

                        Activity: Installation of storm drain pipes

                        • Timeframe: Ongoing

                        Activity: Installation of duct bank trench

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry

                         

                        2601 Main Line Blvd.

                        Activity: Worker van service to/from construction site begins.

                        • Timeframe: Ongoing
                        • Duration: Ongoing


                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        New photos coming soon!


                        All prior construction updates can be found in the Construction Updates Archive.


                        Project Schedule

                        Potomac Yard Metro Station Construction Schedule 2020.04.30

                        Current as of May 29, 2020


                        June 5, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Foundation work at the "knuckle" pier

                        • Timeframe: Ongoing

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Station Platform and Mezzanine  

                        Activity: Formation of foundation walls and the pouring of elevator pit slabs for Headhouse (station)

                        • Timeframe: Ongoing

                        Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                        • Timeframe: Ongoing

                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry

                         

                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        New photos coming soon!


                        All prior construction updates can be found in the Construction Updates Archive.


                        Project Schedule

                        Potomac Yard Metro Station Construction Schedule 2020.04.30

                        Current as of May 29, 2020


                        May 2020

                        MAY 21, 2020 UPDATE

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building 

                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Foundation work at the "knuckle" pier

                        • Timeframe: Ongoing


                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Potomac Greens Traffic Circle   

                        Activity: Installation of planters and landscaping

                        • Timeframe: Through the end of May


                        Station Platform and Mezzanine  

                        Activity: Formation of foundation walls and the pouring of elevator pit slabs for Headhouse (station)

                        • Timeframe: Ongoing


                        Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing


                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry


                        2601 Main Line Blvd.

                        Activity: No new activity

                          

                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site: 

                        PYMS - Construction Photo - Headhouse 2020.04.30

                        Station Headhouse Construction, 1 of 2


                        PYMS - Construction Photo - Headhouse 2 2020.04.30 

                        Station Headhouse Construction, 2 of 2


                        PYMS - Construction Photo - Knuckle Pile Driving 

                        Pile Driving at Knuckle Site

                        MAY 6, 2020 UPDATE

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building 
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Driving piles and welding at "knuckle" location 

                        • Timeframe: Mid-April through Mid-May
                        • Duration: Three weeks 

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Potomac Greens Traffic Circle   

                        Activity: Installation of planters and landscaping

                        • Timeframe: Mid May


                        Station Platform and Mezzanine  

                        Activity: Formation of foundation walls and the pouring of elevator pit slabs for Headhouse (station)

                        • Timeframe: Ongoing

                        Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                        • Timeframe: Ongoing


                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing


                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry


                        2601 Main Line Blvd.

                        Activity: Export of Excavated Material

                        • Timeframe: No new activity

                        April 2020

                        **CONSTRUCTION ACTIVITY NOTICE**

                        After-Hours Construction Begins Sunday, April 26, 2020

                        For three weeks, starting this Sunday, April 26, 2020, Potomac Yard Constructors will be conducting overnight work on WMATA tracks and land in the vicinity of the Carpenter Rd. site entrance. This work requires safe access to the WMATA rail lines and surrounding land while the Metro is not in service, so the window of opportunity for completing this work is limited. For more information, please read this  Noise Variance Notice being disseminated to community members.


                        **CONSTRUCTION ACTIVITY NOTICE**

                        Pile Driving to Occur at "Knuckle" Site

                        Potomac Yard Constructors (PYC) will resume pile driving for the Potomac Yard Metrorail Station on Monday, April 13, 2020. Work will take place northeast of the stormwater detention pond at Dogue Street and Potomac Avenue. This activity is permitted to occur between 9:00 a.m. to 6:00 p.m., Monday through Friday, and 10:00 a.m. to 4:00 p.m., Saturday. PYC anticipates pile driving at this location will take three weeks to complete, weather permitting.


                        April 30, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Driving piles and welding at "knuckle" location 

                        • Timeframe: Mid-April through Mid-May
                        • Duration: Three weeks 

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Potomac Greens Traffic Circle  

                        Activity: Installation of planters and landscaping

                        • Timeframe: Mid May


                        Station Platform and Mezzanine  

                        Activity: Formation of foundation walls and the pouring of elevator pit slabs for Headhouse (station)

                        • Timeframe: Ongoing

                        Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                        • Timeframe: Ongoing

                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry


                        2601 Main Line Blvd.

                        Activity: Export of Excavated Material

                        • Timeframe: No new activity

                         

                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        PYMS - Construction Photo - Headhouse 2020.04.30

                        Station Headhouse Construction, 1 of 2


                        PYMS - Construction Photo - Headhouse 2 2020.04.30

                        Station Headhouse Construction, 2 of 2


                        PYMS - Construction Photo - Knuckle Pile Driving

                        Pile Driving at Knuckle Site

                         

                        Project Schedule

                        Potomac Yard Metro Station Construction Schedule 2020.04.30

                        Current as of April 30, 2020

                        April 21, 2020 Update

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing


                        North Pavilion

                        Activity: Driving piles and welding at "knuckle" location 

                        • Timeframe: Mid-April through Mid-May
                        • Duration: Three weeks 

                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           


                        Potomac Greens Traffic Circle  

                        Activity: Installation of planters and landscaping

                        • Timeframe: Early May

                        Activity: Installation of Solar Powered Flashing Cross Walk Signs 

                        • Timeframe: Mid to Late April


                        Station Platform and Mezzanine  

                        Activity: Formation of foundation walls and the pouring of elevator pit slabs for Headhouse (station)

                        • Timeframe: Ongoing

                        Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                        • Timeframe: On Hold

                        Activity: Grading and installation of Load Transfer Platform (LTP)

                        • Timeframe: Ongoing

                        Activity: Site fill operations

                        • Timeframe: Ongoing
                        • Duration: Several months in periodic three-week segments 
                        • Notes: PYC will bring in clean fill from a quarry


                        2601 Main Line Blvd.

                        Activity: Export of Excavated Material

                        • Timeframe: End of April

                         

                        Construction Gallery

                        The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                        New photos coming soon!


                        All prior construction updates can be found in the Construction Updates Archive.

                        Project Schedule

                        Potomac Yard Metrorail Station Construction Schedule 2019.04.24

                        Current as of April 14, 2020


                        APRIL 14, 2020 UPDATE

                        Construction Work

                        The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                        AC Switchgear Building 
                        Activity: Formation and placement of concrete for the building foundation and walls

                        • Timeframe: Ongoing 
                            

                        North Pavilion 

                        Activity: Driving piles at "knuckle" location 

                        • Timeframe: Mid-April through beginning of May
                        • Duration: Three weeks 


                        Activity: Formation of north pavilion foundation

                        • Timeframe: Ongoing           

                        Potomac Greens Traffic Circle   

                        Activity: Installation of planters and landscaping

                        • Timeframe: Late April


                        Activity: Installation of Solar Powered Flashing Cross Walk Signs 

                        • Timeframe: Mid to Late April

                          Potomac Greens Circle Demolition MOT Image 1 


                          Station Platform and Mezzanine  

                          Activity: Formation of foundation walls and the pouring of elevator pit slabs for Headhouse (station)

                          • Timeframe: Ongoing


                          Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                          • Timeframe: On Hold

                           

                          Activity: Grading and installation of Load Transfer Platform (LTP)

                          • Timeframe: Ongoing


                          Activity: Site fill operations

                          • Timeframe: Ongoing
                          • Duration: Several months in periodic three-week segments 
                          • Notes: PYC will bring in clean fill from a quarry


                          2601 Main Line Blvd.

                          Activity: Export of Excavated Material

                          • Timeframe: Ongoing

                            

                          Construction Gallery

                          The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                          New photos coming soon! 


                          APRIL 9, 2020 UPDATE

                          Construction Work

                          The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                          AC Switchgear Building 
                          Activity: Formation and placement of concrete for the building foundation and walls

                          • Timeframe: Ongoing 
                              

                          North Pavilion 

                          Activity: Driving piles at "knuckle" location 

                          • Timeframe: Mid April through beginning of May (three weeks) 


                          Activity: Formation of north pavilion foundation

                          • Timeframe: Ongoing           

                          Potomac Greens Traffic Circle   

                          Activity: Installation of planters (en route)

                          • Timeframe: Mid April


                          Activity: Installation of pocket park 

                          • Timeframe: Through the end of March


                          Activity: Installation of Solar Powered Flashing Cross Walk Signs 

                          • Timeframe: Through the beginning of April



                            Potomac Greens Circle Demolition MOT Image 1


                            Station Platform and Mezzanine  

                            Activity: Headhouse (Station) foundation work continues with formation of foundation walls and the pouring of elevator pit slabs

                            • Timeframe: Ongoing


                            Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                            • Timeframe: On Hold

                             

                            Activity: Grading and installation of Load Transfer Platform (LTP)

                            • Timeframe: Ongoing


                            Activity: Site fill operations

                            • Timeframe: Ongoing
                            • Duration: Several months in periodic three-week segments 
                            • Notes: PYC will bring in clean fill from a quarry


                            2601 Main Line Blvd.

                            Activity: Export of Excavated Material

                            • Timeframe: Ongoing

                              



                            MARCH 2020

                            MARCH 26, 2020 UPDATE

                            Construction Work

                            The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                            AC Switchgear Building 
                            Activity: Formation and placement of concrete for the building foundation and walls

                            • Timeframe: Ongoing 
                                

                            North Pavilion 
                            Activity: Formation of north pavilion foundation

                            • Timeframe: Ongoing           

                            Potomac Greens Traffic Circle   

                            Activity: Installation of planters 

                            • Timeframe: Mid April


                            Activity: Installation of pocket park 

                            • Timeframe: Through the end of March


                            Activity: Installation of Solar Powered Flashing Cross Walk Signs 

                            • Timeframe: Through the beginning of April



                              Potomac Greens Circle Demolition MOT Image 1


                              Station Platform and Mezzanine  

                              Activity: Foundationwork for Headhouse (Station) begins

                              • Timeframe: Ongoing


                              Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                              • Timeframe: Mid-February through mid-May

                               

                              Activity: Grading and installation of Load Transfer Platform (LTP)

                              • Timeframe: Ongoing


                              Activity: Site fill operations

                              • Timeframe: Ongoing
                              • Duration: Several months in periodic three-week segments 
                              • Notes: PYC will bring in clean fill from a quarry


                              2601 Main Line Blvd.

                              Activity: Export of Excavated Material

                              • Timeframe: Ongoing

                                

                              Construction Gallery

                              The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                Potomac Yard Metrorail Station Construction - AC Switchgear Concrete Pour

                              Removing forms after the concrete pour for the north and east walls of the A/C switchgear building


                              Potomac Yard Metrorail Station Construction - Elevator Shaft Drilling

                              Drilling shafts for the elevator pistons 

                               

                              Potomac Yard Metrorail Station Construction - Forming Grade Beams

                              Forming the grade beams/pile caps (foundations) for north pavilion


                              Potomac Yard Metrorail Construction - Traffic Circle March 2020

                              Paving complete on Potomac Greens Ave.

                                  


                              MARCH 20, 2020 UPDATE

                              Construction Work

                              The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                              AC Switchgear Building 
                              Activity: Formation and placement of concrete for the building foundation and walls

                              • Timeframe: Ongoing 
                                  

                              North Pavilion 
                              Activity: Formation of north pavilion foundation

                              • Timeframe: Ongoing           

                              Potomac Greens Traffic Circle   
                              Activity: Installation of pocket park 

                              • Timeframe: Through the end of March


                              Activity: Installation of Solar Powered Flashing Cross Walk Signs 

                              • Timeframe: Through the beginning of April



                                Potomac Greens Circle Demolition MOT Image 1


                                Station Platform and Mezzanine  

                                Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                                • Timeframe: Mid-February through mid-May

                                 

                                Activity: Installation of Load Transfer Platform (LTP)

                                • Timeframe: Ongoing


                                Activity: Site fill operations

                                • Timeframe: Ongoing
                                • Duration: Several months in periodic three-week segments 
                                • Notes: PYC will bring in clean fill from a quarry


                                2601 Main Line Blvd.

                                Activity: Export of Excavated Material

                                • Timeframe: Ongoing

                                  

                                Construction Gallery

                                The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                  Potomac Yard Metrorail Station Construction - AC Switchgear Concrete Pour

                                Removing forms after the concrete pour for the north and east walls of the A/C switchgear building


                                Potomac Yard Metrorail Station Construction - Elevator Shaft Drilling

                                Drilling shafts for the elevator pistons 

                                 

                                Potomac Yard Metrorail Station Construction - Forming Grade Beams

                                Forming the grade beams/pile caps (foundations) for north pavilion

                                    


                                MARCH 4, 2020 UPDATE

                                Construction Work

                                The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                                AC Switchgear Building 
                                Activity: Formation and placement of concrete for the building foundation and walls

                                • Timeframe: Ongoing 
                                    

                                North Pavilion 
                                Activity: Phase one of pile driving for knuckle structure

                                • Timeframe: Begins mid-March  

                                Potomac Greens Traffic Circle   
                                Activity: Installation of pocket park 

                                • Timeframe: Through the end of March


                                Activity: Installation of Solar Powered Flashing Cross Walk Signs 

                                • Timeframe: Through the beginning of April



                                  Potomac Greens Circle Demolition MOT Image 1


                                  Station Platform and Mezzanine  

                                  Activity: Installation of Controlled Modulus Columns (CMC) with rigid inclusions

                                  • Timeframe: Mid-February through mid-May

                                   

                                  Activity: Site fill operations

                                  • Timeframe: Ongoing
                                  • Duration: Several months in periodic three-week segments 
                                  • Notes: PYC will bring in clean fill from a quarry

                                    

                                  Construction Gallery

                                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                   


                                  PYMSConstructionPotomacGreensDriveTrafficCircleB 

                                  Potomac Greens Drive –  Traffic Circle


                                  PYMSConstructionNPavillionPileDriving2020.02.20 

                                  North Pavilion Pile Driving


                                  PYMSConstructionStationFoundCMCEquip2020.02.20 

                                  Station Foundation – CMC-RI Installation Equipment


                                  PYMSConstructionDeliveryPlatformMaterial2020.02.20 

                                  Delivery of Work Platform Material


                                  PYMSConstructionACSwitchgearConstruction2020.02.20 

                                  A/C Switchgear Building Wall Construction


                                  PYMS Construction - Stabilized Construction Entrance 2020.02.20 

                                  Stabilized Construction Entrance

                                    

                                  City of Alexandria Board of Architectural Review (BAR)

                                  The project completed the BAR review process on February 19, 2020:  

                                  • February 19
                                    • Glass handrail details
                                    • Metal louver connection details
                                    • North Pavilion – stone wall, glazing and lintels 
                                  • January 22
                                  • December 4
                                    • Lighting
                                    • Downspout and gutter locations
                                    • Pedestrian bridge handrail
                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height  
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  



                                  February 2020

                                  **SPECIAL UPDATE**

                                  Left Turn Signal Installed

                                  The left turn signal has been installed at the intersection of Slater’s Lane and Potomac Greens Drive. The light will facilitate turns from eastbound Slater’s Lane to northbound Potomac Greens Drive. 


                                  **CONSTRUCTION ACTIVITY NOTICE**

                                  Pile Driving

                                  Pile driving at the North Pavilion site will begin January 29, 2020, and last for approximately four weeks. Updates will be posted as work progresses.  


                                  FEBRUARY 19, 2020 UPDATE

                                  Construction Work

                                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                                  AC Switchgear Building 
                                  Activity: Formation and placement of concrete for the building foundation and walls

                                  • Timeframe: Ongoing 
                                      

                                  North Pavilion 
                                  Activity: Phase one of pile driving for north pavilion and knuckle structures

                                  • Timeframe: End of January through beginning of March  

                                  Potomac Greens Traffic Circle   
                                  Activity: Installation of pocket park 

                                  • Timeframe: Through the end of March
                                  • Note: Anticipate asphalt work the week of February 17, weather permitting. 

                                  The flow of traffic within this area will follow the Maintenance of Traffic (MOT) plan below: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1  Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  Station Platform and Mezzanine  

                                  Activity: Delivery of rigging, site preparation and installation of Controlled Modulus Columns (CMC) with rigid inclusions

                                  • Timeframe: Mid-February through mid-May

                                   

                                  Activity: Site fill operations

                                  • Timeframe: Ongoing
                                  • Duration: Several months in periodic three-week segments.
                                  • Notes: PYC will bring in clean fill from a quarry.

                                    

                                  Construction Gallery

                                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                  PYMSConstructionPotomacGreensDriveTrafficCircleA 

                                  Potomac Greens Drive - Traffic Circle


                                  PYMSConstructionPotomacGreensDriveTrafficCircleB 

                                  Potomac Greens Drive –  Traffic Circle


                                  PYMSConstructionNPavillionPileDriving2020.02.20 

                                  North Pavilion Pile Driving


                                  PYMSConstructionStationFoundCMCEquip2020.02.20 

                                  Station Foundation – CMC-RI Installation Equipment


                                  PYMSConstructionDeliveryPlatformMaterial2020.02.20 

                                  Delivery of Work Platform Material


                                  PYMSConstructionACSwitchgearConstruction2020.02.20 

                                  A/C Switchgear Building Wall Construction


                                  PYMS Construction - Stabilized Construction Entrance 2020.02.20 

                                  Stabilized Construction Entrance

                                    

                                  City of Alexandria Board of Architectural Review (BAR)

                                  The City completed the station design element design review process with the BAR to ensure they comply with City requirements.  

                                  • February 19
                                    • Glass handrail details
                                    • Metal louver connection details
                                    • North Pavilion – stone wall, glazing and lintels 
                                  • January 22
                                  • December 4
                                    • Lighting
                                    • Downspout and gutter locations
                                    • Pedestrian bridge handrail
                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height  
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  



                                  FEBRUARY 12, 2020 UPDATE

                                  Construction Work

                                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                                  AC Switchgear Building
                                  Activity: Formation and placement of concrete for the building foundation and walls

                                  • Timeframe: Ongoing
                                      

                                  North Pavilion
                                  Activity: Phase one of pile driving for north pavilion and knuckle structures

                                  • Timeframe: End of January through end of February  

                                  Potomac Greens Traffic Circle  
                                  Activity: Reconstruction of paved surfaces 

                                  • Timeframe: Through the end of February
                                  • Note: Anticipate asphalt work the week of February 17, weather permitting. 

                                  After demolition, the flow of traffic will follow the Maintenance of Traffic (MOT) plan below: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1  Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  Station Platform and Mezzanine  

                                  Activity: Delivery of rigging, site preparation and installation of Controlled Modulus Columns (CMC) with rigid inclusions

                                  • Timeframe: Mid-February through mid-May

                                   

                                  Activity: Site fill operations

                                  • Timeframe: Ongoing
                                  • Duration: Several months in periodic three-week segments.
                                  • Notes: PYC will bring in clean fill from a quarry.

                                    

                                  Construction Gallery

                                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                  PYMS Gallery Construction Access Road 1

                                  The construction access road at the mezzanine.


                                  PYMS Gallery Auguring Elevator Shaft Holes 2020.01.15

                                  Auguring holes for the elevator shaft well casings.


                                  PYMS Gallery Storm Line Relocation 2020.01.15

                                  Relocating the existing storm line.


                                  City of Alexandria Board of Architectural Review (BAR)

                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. The next Potomac Yard Metrorail Station presentation will occur at the meeting on  Wednesday, February 19, 2020.

                                  The following design elements have been approved by the BAR:

                                  • January 22
                                  • December 4
                                    • Lighting
                                    • Downspout and gutter locations
                                    • Pedestrian bridge handrail
                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height  
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height 
                                       

                                  January 2020

                                  JANUARY 31, 2020 UPDATE

                                  Construction Work

                                  The dates and work duration periods associated with the following construction work updates are anticipated only and may be subject to change due to weather. 

                                  AC Switchgear Building
                                  Activity: Formation and placement of concrete for the building foundation and walls

                                  • When: Ongoing
                                  • Duration: Ongoing


                                  North Pavilion
                                  Activity: Initiation of pile driving for north pavilion and knuckle structures

                                  • When: Ongoing
                                  • Duration: One Month


                                  Potomac Greens Traffic Circle  
                                  Activity: Demolition, grading, and reconstruction of paved surfaces 

                                  • When: Ongoing (streetlight pole has been removed)
                                  • Duration: Two weeks
                                  • Note: Asphalt work is weather dependent and may impact the start date. 

                                  After demolition, the flow of traffic will follow the Maintenance of Traffic (MOT) plan below: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1  Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  Station Platform and Mezzanine  

                                  Activity: Construction of the access road

                                  • When: Ongoing
                                  • Duration: Three Weeks

                                   

                                  Activity: Site fill operations

                                  • When: Late January
                                  • Duration: Several months in periodic three-week segments.
                                  • Notes: PYC will bring in clean fill from a quarry.

                                    

                                  Construction Gallery

                                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                  PYMS Gallery Construction Access Road 1

                                  The construction access road at the mezzanine.


                                  PYMS Gallery Auguring Elevator Shaft Holes 2020.01.15

                                  Auguring holes for the elevator shaft well casings.


                                  PYMS Gallery Storm Line Relocation 2020.01.15

                                  Relocating the existing storm line.


                                  City of Alexandria Board of Architectural Review (BAR)

                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. The next Potomac Yard Metrorail Station presentation will occur at the meeting on Wednesday, February 19, 2020.

                                  The following design elements have been approved by the BAR:

                                  • January 22
                                  • December 4
                                    • Lighting
                                    • Downspout and gutter locations
                                    • Pedestrian bridge handrail
                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height  
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  



                                  january 17, 2020 Update

                                  Construction Work

                                  The work in the following areas is anticipated to occur through the end of January and into February:  

                                  AC Switchgear Building
                                  Workers will continue to form and place concrete for the building foundation. 


                                  North Pavilion
                                  Activity at the North Pavilion site will continue and include:

                                  • Relocation of the storm line (through the end of January)
                                  • Initiation of pile driving (late January/early February)


                                  Potomac Greens Traffic Circle
                                  The demolition of the Potomac Greens traffic circle has begun. Dominion has started to remove the streetlight. Work will resume once this process is complete.

                                  After demolition, the flow of traffic will follow the Maintenance of Traffic (MOT) plan below: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1 Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  Station Platform and Mezzanine
                                  Construction of the access road is underway. Fill operations are anticipated to begin in late January and occur over several months in periodic three-week segments. PYC will bring in clean fill from a quarry.


                                  Construction Gallery

                                  The following are photos from work recently completed on the Potomac Yard Metrorail Station site:

                                  PYMS Gallery Construction Access Road 1

                                  The construction access road at the mezzanine.


                                  PYMS Gallery Auguring Elevator Shaft Holes 2020.01.15

                                  Auguring holes for the elevator shaft well casings.


                                  PYMS Gallery Storm Line Relocation 2020.01.15

                                  Relocating the existing storm line.


                                  City of Alexandria Board of Architectural Review (BAR)

                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. The next Potomac Yard Metrorail Station presentation will occur at the meeting on Wednesday, January 22, 2020.

                                  The following design elements have been approved by the BAR:

                                  • December 4
                                    • Lighting
                                    • Downspout and gutter locations
                                    • Pedestrian bridge handrail
                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height 
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  


                                  All prior construction updates can be found in the Construction Updates Archive.


                                  Project Schedule

                                  Potomac Yard Metrorail Station Construction Schedule 2020.01.16

                                  Current as of January 15, 2020


                                  December 2019

                                  DECEMBER 6, 2019 UPDATE

                                  Metro's contractor, Potomac Yard Constructors (PYC), continues to prepare for construction of the Potomac Yard Metrorail Station.

                                  The following activities are anticipated to occur through the end of November:  

                                  Traffic Circle Demolition

                                  The demolition of the Potomac Greens traffic circle is still on hold pending the removal of a power pole by Dominion. We will provide an updated timeline once additional details are available.

                                  Work is anticipated to take two weeks once it begins. PYC still plans to implement the following the Maintenance of Traffic (MOT) plan: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1  Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  North Pavilion

                                  Perimeter fencing is being installed at North Pavilion site. Site preparation work will continue into December.


                                  AC Switchgear Building

                                  Site excavation activity will continue into November. Workers are installing the grounding grid, as well as forming and placing the foundation footings. 


                                  Permits and Approvals

                                  Virginia Department of Environmental Quality (DEQ)  
                                  The State Water Control Board Meeting took place on Friday, September 6, 2019. The Board unanimously approved the Virginia Water Protection Permit for the Potomac Yard Metrorail Station Project. The Virginia Department of Environmental Quality issued a Virginia Water Protection (VWP) Individual Permit to the City that day.   The permit and a fact sheet can be found on the Updates and Reports web page.


                                  United States Army Corps of Engineers (USACE)    
                                  The U.S. Army Corps of Engineers (USACE) issued a Clean Water Act (CWA) Section 404 permit to the City of Alexandria for the Potomac Yard Metrorail Station project on November 15, 2019.  The permit and related documents can be found on the Updates and Reports web page.

                                         

                                  City of Alexandria Board of Architectural Review (BAR)    
                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. Staff anticipates plans for the exoskeleton finish and lighting design will be presented for consideration at the next meeting on December 4, 2019.

                                  The following design elements have been approved by the BAR:

                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height  
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  


                                  Station Construction

                                  Activity associated with the establishment of a work zone in wetland area is on hold pending receipt of the United States Army Corps of Engineers (USACE) permit.


                                  RELATED QUESTIONS FROM PYMIG MEETINGS:

                                  Fill Operations

                                  What is PYC going to use for site fill? 
                                  PYC will bring in clean fill from a quarry.

                                  How long will fill operations take? 
                                  Fill operations will occur over several months in periodic three-week segments.


                                  Pile Driving

                                  When is pile driving going to start and for how long? 
                                  Pile driving for the north pavilion and bridge pier is expected to take place during a three-week period between mid-November and mid-December. We understand this coincides with the holiday season and will provide a schedule update once more information is available.


                                  The full presentation and a video of the meeting are available on the PYMIG webpage at  alexandriava.gov/PotomacMetroWorkGroup.

                                  Next PYMIG Meeting:  Tuesday, November 19 from 7 – 9 p.m. at the Charles Houston Recreation Center Multi-Purpose Room


                                  PROJECT ACTIVITY COMPLETED TO DATE

                                  Site Preparation

                                  • Office complex established and occupied
                                  • Work zone at Carpenter Rd. established
                                  • Non-wetland areas cleared
                                  • Station design continued
                                  • Documentation of existing conditions completed


                                  AC Switchgear Building

                                  • Access road to AC Switchgear building installed
                                  • Subgrade-depth excavation at AC Switchgear building completed
                                  • Electrical duct bank and conduit stub outs installed


                                  2601 Main Line Blvd.

                                  • Parking lot grading completed
                                  • Infrastructure installation started
                                  • Fencing and mesh wrap installed
                                  • Parking lot and temporary sidewalks paved
                                  • Access ramps installed


                                  ALL PRIOR CONSTRUCTION UPDATES CAN BE FOUND IN THE CONSTRUCTION UPDATES ARCHIVE.


                                  November 2019 

                                  NOVEMBER 5, 2019 UPDATE

                                  Metro's contractor, Potomac Yard Constructors (PYC), continues to prepare for construction of the Potomac Yard Metrorail Station.

                                  The following activities are anticipated to occur through the end of November:  

                                  Traffic Circle Demolition

                                  The demolition of the Potomac Greens traffic circle is still on hold pending the removal of a power pole by Dominion. We will provide an updated timeline once additional details are available.

                                  Work is anticipated to take two weeks once it begins. PYC still plans to implement the following the Maintenance of Traffic (MOT) plan: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1  Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  AC Switchgear Building

                                  Site excavation activity will continue into November. Workers are installing the grounding grid, as well as forming and placing the foundation footings. 


                                  Permits and Approvals

                                  Virginia Department of Environmental Quality (DEQ)  
                                  The State Water Control Board Meeting took place on Friday, September 6, 2019. The Board unanimously approved the Virginia Water Protection Permit for the Potomac Yard Metrorail Station Project. The Virginia Department of Environmental Quality issued a Virginia Water Protection (VWP) Individual Permit to the City that day.


                                  United States Army Corps of Engineers (USACE)  
                                  The USACE is completing its review of the Potomac Yard Metrorail Station Joint Permit Application. Staff anticipates the Army Corps will announce its decision in the coming weeks.


                                  City of Alexandria Board of Architectural Review (BAR)    
                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. Staff anticipates plans for the exoskeleton finish and lighting design will be presented for consideration at the next meeting on December 4, 2019.

                                  The following design elements have been approved by the BAR:

                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height  
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  


                                  Station Construction

                                  Activity associated with the establishment of a work zone in wetland area is on hold pending receipt of the United States Army Corps of Engineers (USACE) permit.



                                  RELATED QUESTIONS FROM PYMIG MEETINGS:

                                  Fill Operations

                                  What is PYC going to use for site fill? 
                                  PYC will bring in clean fill from a quarry.

                                  How long will fill operations take? 
                                  Fill operations will occur over several months in periodic three-week segments.


                                  Pile Driving

                                  When is pile driving going to start and for how long? 
                                  Pile driving for the north pavilion and bridge pier is expected to take place during a three-week period between mid-November and mid-December. We understand this coincides with the holiday season and will provide a schedule update once more information is available.



                                  The full presentation and a video of the meeting are available on the PYMIG webpage at  alexandriava.gov/PotomacMetroWorkGroup.

                                  Next PYMIG Meeting:  Tuesday, November 19 from 7 – 9 p.m. at the Charles Houston Recreation Center Multi-Purpose Room



                                  PROJECT ACTIVITY COMPLETED TO DATE

                                  Site Preparation

                                  • Office complex established and occupied
                                  • Work zone at Carpenter Rd. established
                                  • Non-wetland areas cleared
                                  • Station design continued
                                  • Documentation of existing conditions completed


                                  AC Switchgear Building

                                  • Access road to AC Switchgear building installed
                                  • Subgrade-depth excavation at AC Switchgear building completed
                                  • Electrical duct bank and conduit stub outs installed


                                  2601 Main Line Blvd.

                                  • Parking lot grading completed
                                  • Infrastructure installation started
                                  • Fencing and mesh wrap installed
                                  • Parking lot and temporary sidewalks paved
                                  • Access ramps installed



                                  ALL PRIOR CONSTRUCTION UPDATES CAN BE FOUND IN THE CONSTRUCTION UPDATES ARCHIVE.


                                  Project Schedule

                                  PYMS Construction - Look Ahead Schedule 2019.10.24 

                                  Current as of October 31, 2019


                                  October 2019 

                                  October 30, 2019 Update

                                  Metro's contractor, Potomac Yard Constructors (PYC), continues to prepare for construction of the Potomac Yard Metrorail Station.

                                  The following activities are anticipated to occur through the end of October:  

                                  Traffic Circle Demolition

                                  The demolition of the Potomac Greens traffic circle is currently on hold pending the removal of a power pole by Dominion. We will provide an updated timeline once additional details are available.

                                  Work is anticipated to take two weeks once it begins. PYC still plans to implement the following the Maintenance of Traffic (MOT) plan: 

                                  Click on each thumbnail to enlarge the image.

                                  Potomac Greens Circle Demolition MOT Image 1 Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  AC Switchgear Building

                                  Site excavation activity will continue into November. Workers are installing the grounding grid, as well as forming and placing the foundation footings.


                                  2601 Main Line Blvd.

                                  PYC is required to provide off-street parking for their workers, trucks, and trailers as a condition of the Development Special Use Permit (DSUP) approved by City Council. This lot will be located at 2601 Main Line Blvd., which is on an undeveloped block bordered by Main Line Blvd. to the west, Potomac Ave. to the east, Maskell St. to the north, and Swann Ave. to the south. Activity towards the end of this month may include paving, the installation of fencing, and formation of access ramps. The only point of access will be off Potomac Ave.

                                  Click on the thumbnail to enlarge the image.

                                  2601 Main Line Blvd Map


                                  Permits and Approvals

                                  Virginia Department of Environmental Quality (DEQ) 
                                  The State Water Control Board Meeting took place on Friday, September 6, 2019. The Board unanimously approved the Virginia Water Protection Permit for the Potomac Yard Metrorail Station Project. The Virginia Department of Environmental Quality issued a Virginia Water Protection (VWP) Individual Permit to the City that day.


                                  United States Army Corps of Engineers (USACE) 
                                  The USACE is completing its review of the Potomac Yard Metrorail Station Joint Permit Application. Staff anticipates the Army Corps will announce its decision in the coming weeks.


                                  City of Alexandria Board of Architectural Review (BAR)   
                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. Staff anticipates plans for the exoskeleton finish and lighting design will be presented for consideration at the next meeting in December 2019.

                                  The following design elements have been approved by the BAR:

                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height 
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale 
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  


                                  Haul Routes

                                  The following haul routes have been approved for use:

                                  I-495/Potomac Greens 

                                  PYMS Construction - Haul Route - I-495 Potomac Greens

                                  To Site:

                                  • I-495 to US-1 N (S. Patrick St.)
                                  • North on US-1 N to Slaters Ln.
                                  • Right onto Slaters Ln.
                                  • East on Slaters Ln. to Potomac Greens Dr.
                                  • Left onto Potomac Greens Dr.
                                  • North on Potomac Greens Dr.

                                  From Site:

                                  • South on Potomac Greens Dr. to Slaters Ln.
                                  • Right onto Slaters Ln.
                                  • West on Slaters Ln.
                                  • Right at fork and under overpass to US-1 S (N. Henry St.)
                                  • Right onto US-1 S
                                  • South on US-1 to I-495 


                                  I-395/Potomac Greens

                                  PYMS Construction - Haul Route - I-395 Potomac Greens 

                                  To Site:

                                  • I-395 to SR-120 (S. Glebe Rd.)
                                  • East on SR-120 to US-1 S (Richmond Hwy.)
                                  • Right onto US-1 S
                                  • South on US-1 S to Slaters Ln.
                                  • Left onto Slaters Ln.
                                  • East on Slaters Ln. to Potomac Greens Dr.
                                  • Left onto Potomac Greens Dr.
                                  • North on Potomac Greens Dr.

                                  From Site:

                                  • South on Potomac Dr. to Slaters Ln.
                                  • Right onto Slaters Ln.
                                  • Left at fork and up ramp to US-1 N (Richmond Hwy.)
                                  • Right onto US-1 N
                                  • North on US-1 N to SR-120 (S. Glebe Rd.)
                                  • Left on SR-120
                                  • West on SR-120 to I-395


                                  I-495/2601 Main Line Blvd.

                                  PYMS Construction - Haul Route - I-495 2601 Main Line

                                  To Site:

                                  • I-495 to US-1 N (S. Patrick St.)
                                  • North on US-1 N to E. Glebe Rd.
                                  • Right onto E. Glebe Rd.
                                  • East on E. Glebe Rd. to Potomac Ave.
                                  • Right onto Potomac Ave.
                                  • South on Potomac Ave. past Maskell St.
                                  • Site entrance located on right, mid-block

                                  From Site:

                                  • Right onto Potomac Ave.
                                  • South on Potomac Ave. to US-1
                                  • Left onto US-1 S (Richmond Hwy.)
                                  • South on US-1 S to I-495


                                  I-395/2601 Main Line Blvd.

                                  PYMS Construction - Haul Route - I-395 2601 Main Line Blvd

                                  To Site:

                                  • I-395 to SR-120 (S. Glebe Rd.)
                                  • East on SR-120 to US-1 S (Richmond Hwy.)
                                  • Right onto US-1 S
                                  • South on US-1 S to E. Glebe Rd.
                                  • Left onto E. Glebe Rd.
                                  • East on E. Glebe Rd. to Potomac Ave.
                                  • Right onto Potomac Ave.
                                  • South on Potomac Ave. past Maskell St.
                                  • Site entrance located on right, mid-block

                                  From Site:

                                  • Right onto Potomac Ave.
                                  • South on Potomac Ave. to US-1
                                  • Right onto US-1 N (Richmond Hwy.)
                                  • North on US-1 N to SR-120 (S. Glebe Rd.)
                                  • Left on SR-120
                                  • West on SR-120 to I-395


                                  Potomac Greens/2601 Main Line Blvd.  

                                  PYMS Construction - Haul Route - Potomac Greens 2601 Main Line Blvd

                                  To Potomac Greens from 2601 Main Line Blvd.:

                                  • Right onto Potomac Ave.
                                  • South on Potomac Ave. to US-1
                                  • Left onto US-1 S (Richmond Hwy.)
                                  • South on US-1 S to Slaters Ln.
                                  • Left onto Slaters Ln.
                                  • East on Slaters Ln. to Potomac Greens Dr.
                                  • Left onto Potomac Greens Dr.
                                  • North on Potomac Greens Dr.

                                  To 2601 Main Line Blvd. from Potomac Greens:

                                  • South on Potomac Dr. to Slaters Ln.
                                  • Right onto Slaters Ln.
                                  • West on Slaters Ln.
                                  • Left at the fork and up ramp to US-1 N (Richmond Hwy.)
                                  • Right onto US-1 N
                                  • North on US-1 N to E. Glebe Rd.
                                  • East on E. Glebe Rd. to Potomac Ave.
                                  • Right onto Potomac Ave.
                                  • South on Potomac Ave. past Maskell St.
                                  • Site entrance located on right, mid-block


                                  Station Construction

                                  Activity associated with the establishment of a work zone in wetland area is on hold pending receipt of the United States Army Corps of Engineers (USACE) permit.



                                  Related Questions from the PYMIG Meeting on September 25, 2019:

                                  Fill Operations

                                  What is PYC going to use for site fill?
                                  PYC will bring in clean fill from a quarry.

                                  How long will fill operations take?
                                  Fill operations will occur over several months in periodic three-week segments.

                                  What roads will the trucks travel on to access the site?
                                  The hauling route is undergoing review by the City and will be posted to this site once approved.


                                  Construction Worker Parking and Site Access

                                  How will the construction workers travel between 2601 Main Line Blvd. and the construction site?
                                  Workers will be transported to and from the construction site via private shuttles.

                                  Will the construction workers be able to park on the street?
                                  Workers are not allowed to park and access the site from the street. If you witness a violation of this rule, please contact Jason Scofi at jason.scofi@alexandriava.gov or 703.746.4060.


                                  Pile Driving

                                  When is pile driving going to start and for how long?
                                  Pile driving for the north pavilion and bridge pier is expected to take place during a three-week period between mid-November and mid-December. We understand this coincides with the holiday season and will provide a schedule update once more information is available.



                                  The full presentation and a video of the meeting are available on the PYMIG webpage at alexandriava.gov/PotomacMetroWorkGroup.

                                  Next PYMIG Meeting: Tuesday, November 19 from 7 – 9 p.m. at the Charles Houston Recreation Center Multi-Purpose Room



                                  Project Activity Completed to Date

                                  Site Preparation

                                  • Office complex established and occupied
                                  • Work zone at Carpenter Rd. established
                                  • Non-wetland areas cleared
                                  • Station design continued
                                  • Documentation of existing conditions completed

                                  AC Switchgear Building

                                  • Access road to AC Switchgear building installed
                                  • Subgrade-depth excavation at AC Switchgear building completed
                                  • Electrical duct bank and conduit stub outs installed


                                  2601 Main Line Blvd.

                                  • Parking lot grading completed
                                  • Infrastructure installation started



                                  OCTOBER 21, 2019 UPDATE

                                  Metro's contractor, Potomac Yard Constructors (PYC), continues to prepare for construction of the Potomac Yard Metrorail Station.

                                  The following activities are anticipated to occur through the end of October:

                                  Traffic Circle Demolition

                                  The demolition of the Potomac Greens traffic circle is currently on hold pending the removal of a power pole by Dominion. We will provide an updated timeline once additional details are available.

                                  Work is anticipated to take two weeks once it begins. PYC still plans to follow the Maintenance of Traffic (MOT) below:

                                  Potomac Greens Circle Demolition MOT Image 1 Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  AC Switchgear Building

                                  Site excavation activity will continue into November. Workers are installing the grounding grid, as well as forming and placing the foundation footings.


                                  2601 Main Line Blvd.

                                  PYC is required to provide off-street parking for their workers, trucks, and trailers as a condition of the Development Special Use Permit (DSUP) approved by City Council. This lot will be located at 2601 Main Line Blvd., which is on an undeveloped block bordered by Main Line Blvd. to the west, Potomac Ave. to the east, Maskell St to the north, and Swann Ave. to the south. Activity towards the end of this month may include paving, the installation of fencing, and formation of access ramps. The only point of access will be off Potomac Ave.

                                  2601 Main Line Blvd Map


                                  Station Construction

                                  Activity associated with the establishment of a work zone in wetland area is on hold pending receipt of the United States Army Corps of Engineers (USACE) permit.


                                  RELATED QUESTIONS FROM THE PYMIG MEETING ON SEPTEMBER 25, 2019:

                                  Fill Operations

                                  What is PYC going to use for site fill? 
                                  PYC will bring in clean fill from a quarry.

                                  How long will fill operations take? 
                                  Fill operations will occur over several months in periodic three-week segments.

                                  What roads will the trucks travel on to access the site? 
                                  The hauling route is undergoing review by the City and will be posted to this site once approved.


                                  Construction Worker Parking and Site Access

                                  How will the construction workers travel between 2601 Main Line Blvd. and the construction site? 
                                  Workers will be transported to and from the construction site via private shuttles.

                                  Will the construction workers be able to park on the street? 
                                  Workers are not allowed to park and access the site from the street. If you witness a violation of this rule, please contact Jason Scofi at  jason.scofi@alexandriava.gov or 703.746.4060.


                                  Pile Driving

                                  When is pile driving going to start and for how long? 
                                  Pile driving for the north pavilion and bridge pier is expected to take place during a three-week period between mid-November and mid-December. We understand this coincides with the holiday season and will provide a schedule update once more information is available.


                                  Permitting and Approvals

                                  What is the status of the project's permits?

                                  Virginia Department of Environmental Quality (DEQ) 
                                  The State Water Control Board Meeting took place on Friday, September 6, 2019. The Board unanimously approved the Virginia Water Protection Permit for the Potomac Yard Metrorail Station Project. The Virginia Department of Environmental Quality issued a Virginia Water Protection (VWP) Individual Permit to the City that day.

                                  United States Army Corps of Engineers (USACE) 
                                  The USACE is completing its review of the Potomac Yard Metrorail Station Joint Permit Application. Staff anticipates the Army Corps will issue its permit in the coming weeks.

                                  City of Alexandria Board of Architectural Review (BAR)  
                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. Staff anticipates plans for the exoskeleton finish and lighting design will be presented for consideration at the next meeting.

                                  The following design elements have been approved by the BAR:

                                  • October 16
                                    • North pavilion: footprint, mass, scale, and height
                                  • September 4
                                    • Bridge, platform, and mezzanine: mass, scale, and materials sample board
                                  • July 24
                                    • Piers, mezzanine, platform roofs: mass and scale
                                  • July 10
                                    • Project architectural character, footprint, scale, and height  

                                  The full presentation and a video of the meeting are available on the PYMIG webpage at  alexandriava.gov/PotomacMetroWorkGroup.

                                  Next PYMIG Meeting:  Tuesday, October 29 from 7 – 9 p.m. at the Charles Houston Recreation Center Multi-Purpose Room


                                  PROJECT ACTIVITY COMPLETED TO DATE

                                  Site Preparation

                                  • Office complex established
                                  • Work zone at Carpenter Rd. established
                                  • Non-wetland areas cleared
                                  • Station design continued
                                  • Documentation of existing conditions completed

                                  AC Switchgear Building

                                  • Access road to AC Switchgear building installed
                                  • Subgrade-depth excavation at AC Switchgear building completed


                                  Project Schedule

                                  PYMS Construction - Look Ahead Schedule 2019.10.09  

                                  Current as of October 11, 2019




                                  OCTOBER 9, 2019 UPDATE

                                  Metro's contractor, Potomac Yard Constructors (PYC), continues to prepare for construction of the Potomac Yard Metrorail Station.

                                  The following activities are anticipated to occur through the end of October:  

                                  Traffic Circle Demolition

                                  Starting Monday, October 21, workers will begin demolition of the Potomac Greens traffic circle. This process is anticipated to take two weeks. The following Maintenance of Traffic (MOT) plan will be implemented during that time:

                                  Potomac Greens Circle Demolition MOT Image 1 Potomac Greens Circle Demolition MOT Image 2 Potomac Greens Circle Demolition MOT Image 3


                                  AC Switchgear Building

                                  Site excavation activity will continue over the next two weeks. Workers will install the grounding grid and start to form and place the foundation footings.


                                  2601 Main Line Blvd.

                                  PYC is required to provide off-street parking for their workers, trucks, and trailers as a condition of the Development Special Use Permit (DSUP) approved by City Council. This lot will be located at 2601 Main Line Blvd., which is on an undeveloped block bordered by Main Line Blvd. to the west, Potomac Ave. to the east, Maskell St to the north, and Swann Ave. to the south. Activity towards the end of this month may include paving, the installation of fencing, and formation of access ramps. The only point of access will be off Potomac Ave.

                                  2601 Main Line Blvd Map


                                  Station Construction

                                  Activity associated with the establishment of a work zone in wetland area is on hold pending receipt of the United States Army Corps of Engineers (USACE) permit.


                                  RELATED QUESTIONS FROM THE PYMIG MEETING ON SEPTEMBER 25, 2019:

                                  Fill Operations

                                  What is PYC going to use for site fill? 
                                  PYC will bring in clean fill from a quarry.

                                  How long will fill operations take? 
                                  Fill operations will occur over several months in periodic three-week segments.

                                  What roads will the trucks travel on to access the site? 
                                  The hauling route is undergoing review by the City and will be posted to this site once approved.


                                  Construction Worker Parking and Site Access

                                  How will the construction workers travel between 2601 Main Line Blvd. and the construction site? 
                                  Workers will be transported to and from the construction site via private shuttles.

                                  Will the construction workers be able to park on the street? 
                                  Workers are not allowed to park and access the site from the street. If you witness a violation of this rule, please contact Jason Scofi at  jason.scofi@alexandriava.gov or 703.746.4060.


                                  Pile Driving

                                  When is pile driving going to start and for how long? 
                                  Pile driving for the north pavilion and bridge pier is expected to take place during a three-week period between mid-November and mid-December. We understand this coincides with the holiday season and will provide a schedule update once more information is available.


                                  Permitting and Approvals

                                  What is the status of the project's permits?

                                  Virginia Department of Environmental Quality (DEQ) 
                                  The State Water Control Board Meeting took place on Friday, September 6, 2019. The Board unanimously approved the Virginia Water Protection Permit for the Potomac Yard Metrorail Station Project. The Virginia Department of Environmental Quality issued a Virginia Water Protection (VWP) Individual Permit to the City that day.


                                  United States Army Corps of Engineers (USACE) 
                                  The USACE is completing its review of the Potomac Yard Metrorail Station Joint Permit Application. Staff anticipates the Army Corps will issue its permit in the coming weeks.


                                  City of Alexandria Board of Architectural Review (BAR) 
                                  The City continues to review station design elements with the BAR to ensure they comply with City requirements. Staff anticipates plans for the exoskeleton finish and lighting design will be presented for consideration at the next meeting on October 16, 2019.

                                  The following design elements have been approved by the BAR:

                                  • September 4
                                    • Mass and scale (finalized)
                                    • Materials sample board:
                                    • Bridge
                                    • Platform
                                    • Mezzanine
                                  • July 24
                                    • Mass and scale of the piers
                                    • Mass and scale of mezzanine
                                    • Mass and scale of platform roofs
                                  • July 10
                                    • Project height
                                    • Project scale
                                    • Project footprint
                                    • Architectural character 

                                  The full presentation and a video of the meeting are available on the PYMIG webpage at  alexandriava.gov/PotomacMetroWorkGroup.

                                  Next PYMIG Meeting:  Tuesday, October 29 from 7 – 9 p.m. at the Charles Houston Recreation Center Multi-Purpose Room


                                  PROJECT ACTIVITY COMPLETED TO DATE

                                  Site Preparation

                                  • Office complex established
                                  • Work zone at Carpenter Rd. established
                                  • Non-wetland areas cleared
                                  • Station design continued
                                  • Documentation of existing conditions completed

                                  AC Switchgear Building

                                  • Access road to AC Switchgear building installed
                                  • Subgrade-depth excavation at AC Switchgear building completed

                                  August 2019 

                                  AUGUST 20, 2019 UPDATE

                                  The City of Alexandria will host a Board of Architectural Review (BAR) work session on the Potomac Yard Metrorail Station design prior to the regularly scheduled BAR hearing on Wednesday, September 4, 2019. Potomac Yard Contractors will be on hand answer questions from the public about the station design. The public can also take virtual tours of the station design prior to this meeting via the links below. Details on the workshop can be found on the  Potomac Yard Metrorail Station Public Engagement webpage.  

                                  The virtual tours are available to view online:



                                  August 16, 2019 Update

                                  Potomac Yard Constructors (PYC) continues to establish an on-site operations hub:

                                  •  The office trailers site and access road grading is complete; 
                                  •  Fence wraps are in place; and, 
                                  •  Installation of office trailer utilities continues.

                                  Upcoming on-site work will include:

                                  •  Construction of an AC switchgear building;
                                  •  Installation of utilities under WMATA tracks; and,
                                  •  Documentation of existing conditions.


                                  Noise Variance Permit Issued

                                  A Noise Variance Permit has been issued to PYC for the installation of cable and utilities under the existing WMATA tracks. This permit is valid from August 13 until September 12, 2019, and allows for work between 7 a.m. and 7 p.m., Monday through Sunday. Excavators, rollers, loaders, and other tools will be in use on site. Per the permit conditions, PYC is required to provide advance notice of this work to all residents located within 300 yards of the site.

                                  For more information about the City’s Noise Code, see Construction Noise.


                                  July 2019

                                  July 25, 2019 - Office Trailer Preparations

                                  Potomac Yard Constructors (PYC) is taking the initial steps to commence on-site operations. You may begin to see activity in the area designated for the PYC office trailers. This includes:

                                  • Delivery of grading equipment and office trailers
                                  • Grading of the office trailers site and access road
                                  • Installation of office trailer utilities