Taylor Run Infrastructure Stabilization Project
Project Summary
Phase: Design
Status: Active
Small Area Plan: Taylor Run/Duke Street
Department: Transportation & Environmental Services
Project Description
The Taylor Run Infrastructure Stabilization Project focuses on protecting vulnerable infrastructure and reducing erosion along sections of Taylor Run through a targeted, minimal intervention approach. Based on the recommendations of the community stakeholder group that were adopted by the City Council, in lieu of the original stream restoration project, the City is pursuing strategic stabilization work to stabilize critical storm and sanitary sewer infrastructure for specific areas of concern discussed through community input.
Project Goals:
- Protect critical, at-risk infrastructure (e.g. sewer pipes, manholes, outfalls, and trails).
- Preserve and protect mature trees and wetlands.
- Minimize the limits of disturbance, vegetation removal, and construction impacts.
Recommendations approved by City Council: Taylor Run CBG Recommendations
This focused stabilization approach was developed in collaboration with community stakeholders through the Stream Health Improvement Community Collaboration. This design follows the City Council approved recommendations developed with the Consensus Building Group. The project team is now refining the proposed solutions and identifying construction needs.
Schedule
- Planning: January 2023 – October 2024
- Design: October 2024 – September 2027
- Construction*: September 2027 – August 2028
*The Construction phase begins with the hiring of a construction contractor.
Construction site activity typically starts a few months later.
Funding
Project Budget: $2,155,000
- Planning: Stream Health Improvement Community Collaboration
- Design: $350,000
- Construction: $1,805,000
Learn more about the City of Alexandria's Fiscal Year Budget.
Design
The 60% revised design plans was delivered to the City on November 19, 2026. The project team held a public meeting at 2900 Business Center Drive and virtually to share the plans with the community. Attendees had the opportunity to ask questions and provide feedback.
Taylor Run Proposed Practices Handout
Basis of Design Report and Appendices
- Taylor Run Infrastructure Stabilization 60% Basis of Design Report
- Appendix A - Tree Inventory
- Appendix B - CCTV Assessment Report
- Appendix C - Geotechnical Assessment Report
- Appendix D - Wetland Delineation Report
- Appendix E - Site Photographs
- Appendix F - Hydrology and Hydraulics
- Appendix G - Joint Permit Application Package
- Appendix H - Stormwater Pollution Prevention Plan
- Appendix I - Adverse Impact Verification Memorandum
- Appendix J - Construction Specification
- Appendix K - Cost Estimate
- Appendix L - 60% Design Plans
The 60% design plans was delivered to the City in July 2026. The project team held a public meeting on July 20, 2026 and held a on-site walkthrough with the public on August 8, 2026.
Basis of Design Report and Appendices
- Taylor Run Infrastructure Stabilization 60% Basis of Design Report
- Appendix A - Tree Inventory
- Appendix B - CCTV Assessment Report
- Appendix C - Geotechnical Assessment Report
- Appendix D - Wetland Delineation Report
- Appendix E - Site Photographs
- Appendix F - Hydrology and Hydraulics
- Appendix G - Joint Permit Application Package
- Appendix H - Stormwater Pollution Prevention Plan
- Appendix I - Adverse Impact Verification Memorandum
- Appendix J - Construction Specification
- Appendix K - Cost Estimate
- Appendix L - 60% Design Plans
The 30% Basis of Design Report and Plan Set was delivered to the City in October 2025. The project team held a community meeting in November 2025 to present the conceptual 30% design. A site walk was held in December 2025 to review the full site design in-field with community members.
Basis of Design Report and Appendices
- Taylor Run Infrastructure Stabilization 30% Basis of Design Report
- Appendix A - Tree Inventory
- Appendix B - CCTV Assessment Report
- Appendix C - Geotechnical Assessment Report
- Appendix D - Site Photographs
- Appendix E - Hydrology and Hydraulics
- Appendix F - Cost Estimate
- Appendix G - 30% Design Plans
Past Community Engagement
Meeting Type | Date | Recording | Presentation Slides | Q&A Record | Public Comment Response |
|---|---|---|---|---|---|
| 60% Revised Design Community Meeting | 11/19/2026 | 60% Revised Design Zoom Recording | 60% Revised Design Presentation Slides | Community Feedback Form *Open through Saturday, December 19* | |
| 60% Design Community Meeting | 07/20/26 | 60% Design Zoom Recording | 60% Design Presentation Slides | ||
| Outfall 1 Design Meeting | 03/26/26 | Outfall 1 Design Zoom Recording | Outfall 1 Design Presentation Slides | Outfall 1 Q&A Record | Outfall 1 Design Comment Response |
| 30% Design Community Meeting | 11/13/25 | 30% Design Zoom Recording | 30% Design Presentation Slides | 30% Design Comment Response |