Del Ray West Manhole and Mainline Rehabilitation
Project Summary
Current Phase: Planning
Sponsor Project Manager: Lu Zhang, Transportation & Environmental Services
Managing Project Manager: Anup Gautam, Project Implementation
Project Description
The Del Ray West Manhole and Mainline Rehabilitation project provides for the inspection and rehabilitation of sewer mains and manholes in the Del Ray West area, generally located between Commonwealth Avenue and Russell Road from West Glebe Road to King Street. This work is being done as part of the City's Sanitary Sewer Asset Renewal Program.
This project is currently in the planning phase. Planning phase activities consist of inspection of manholes and inspection of City sanitary sewer mains using closed circuit television (CCTV). Inspection data collected is then reviewed to determine what sewers and manholes require rehabilitation, with most of the rehabilitation being trenchless (no digging). The planning phase is being managed by the Department of Transportation and Environmental Services' Sanitary Infrastructure Division. Following planning, the project will be transferred to the City's Department of Project Implementation for design and construction.
This project extends the useful life of the existing life of the existing sanitary sewer system, reduces the amount of infiltration and inflow (I&I) that enters the sanitary sewer system and reduces the need for emergency repairs.
Project Funding
Project Budget
Total Budget: $5.6 million
Planning Phase: $2 million (Includes inspection of City-owned sewer laterals.)
Design Phase: $100,000
Construction Phase: $3.5 million
Funding Breakdown
Funding for the Sanitary Sewer Asset Renewal Program comes from the City's Capital Improvement Program for Sanitary Sewers.
Project Schedule
Planning: June 2022 - August 2024
Design: September 2024 - December 2025
Construction: January 2026 - December 2026
Planning Phase
Planning Overview
- Field Inspection/ Condition Assessment - Inspected small diameter sewer mains and structures, (manholes, inlets, and catch basins) using pole camera and CCTV camera per National Association of Sewer Service Companies (NASSCO) guidelines to document structural and operation and maintenance (O&M) conditional of each asset.
- Rehabilitation Recommendation - Reviewed inspection reports and photos to determine sewer assets requiring rehabilitation and proper rehabilitation technology.
- Cost Estimate - A planning level cost estimate was performed for design and construction services.
Planning Public Outreach
Residents and businesses are notified of the project through public signage, along with door hangars for when work is occurring in their area.