Old Town Sewer Assessment and Rehabilitation Program
Old Town Sewer Assessment and Rehabilitation Program
This project provides for the condition assessment of all sewers in the Old Town area (including the combined sewer area) of the City and remediation of structurally deficient sewers and sewer structures. This project will be completed in several phases, starting with inspections. The first phase of inspections was completed in June 2020 and consisted of physical inspections of all manholes and inlets in the Old Town area. This second phase of inspections was completed in June 2021 and included CCTV inspection of all sewers in the northern half of the Old Town area. Currently, CCTV inspections are ongoing in the southern half of the Old Town area, which are anticipated to be completed by June 2023. Once these inspections are completed, the rehabilitation phase of the project will commence.
Read more about the Old Town Sewer Assessment and Rehabilitation Program or contact Lu Zhang at 703.746.4289.