Charles Barrett Recreation Center Playground Renovation

Page updated on Feb 20, 2025 at 5:33 PM

Contact

Judy Lo, Principal Planner
judy.lo@alexandriava.gov

Parks

  • Overview
    • General Information
    • ParkLink
  • Planning & Projects
    • Capital Projects
    • Open Space
    • Park Planning
  • Park Operations
    • Park Operations
    • Natural Resources
    • Trees & Urban Forestry
  • Community Gardens
  • Dog Parks
  • Park Rentals & Permits

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Location

1115 Martha Custis Drive

Description

The existing Charles Barrett playground is scheduled to be fully renovated. In 2018, over 270 students and parents completed a playground design survey to

Charles Barrett Playground Plan

provide input on the uses and playground needs. The new playground will accommodate group activities, with a variety of modern climbing, spinning and sliding equipment. A new obstacle course designed specifically for children will provide other fitness opportunities. The site's stormwater drainage systems will also undergo upgrades, and may feature rain gardens to capture and filter rainwater. To support student drop off and pickup and improve access to the play area, new pathways and seating will be located around the playground.

Funding

City Capital Improvement Program (CIP)

Project Status

Project is substantially complete. Playground opened May 2024.

Project Schedule

  • Engineering Design and Regulatory Permitting: July - December 2021
  • Construction Procurement: Fall 2022 - Spring 2023
  • Construction: Fall 2023
  • Expected Completion: 2023 - 2024

Design Documents

  • Charles Barrett Recreation Playground Design
  • Charles Barrett Recreation Play Equipment Colors

Community Updates

  • November 2024
    The project has been substantially complete since May. Over the summer new fencing and plantings were installed. Minor punchlist items are being addressed this fall. The new plantings have a one year establishment guarantee.
  • May 2024
    The playground safety inspections were completed and outstanding safety items were addressed. The general contractor also completed the major punch list items. The playground re-opened to the public on May 3.  Orange snow fence/silt fence have been installed to protect the newly seeded areas, and will stay up for the next 3-4 weeks until grass is fully established. New fencing, trees, and landscaping are scheduled for June and July.
  • April 2024
    Inspections which include safety inspections for the playground equipment and safety surfacing will be conducted, and a punch list will be created. The contractor will works towards addressing the punch list items. A soft opening is anticipated for mid-late April. 
  • March 2024
    Installation of the poured in place safety surfacing started on March 12 and was completed on March 15.  The concrete walkways and site furnishings were installed. The contractor is completing the remaining stormwater components, and will begin site restoration. A soft opening is anticipated for mid-April. New fencing, trees and landscape plantings will be scheduled later this spring.
  • February 2024
    The playground equipment and shade structures have been installed. The contractor completed the stormwater management system connections and will begin installation of the concrete walkways, site furnishings and dry swale BMP in late February Installation of the poured in place safety surfacing is weather dependent and will require warmer temperatures for installation, most likely mid-March. New fencing, trees and landscape plantings will be scheduled this spring.
  • January 2024
    Mobilization began in early November with the installation of the erosion and sediment controls and site surveying. Demolition of the old playground was completed and the site was excavated and re-graded. In December, the playground equipment installation commenced and will continue throughout the month of January. The contractor will also begin installation of the stormwater management systems which include new piping and a dry swale BMP. While most of the playground equipment has been installed, the installation of the poured in place safety surfacing is weather dependent and will require warmer temperatures for installation. 
  • October 2023 
    In early September a contract was awarded to the Bright Construction Group, Inc. based in Falls Church, VA. Notice to Proceed was issued to the Contractor on September 19 and a pre-construction meeting was held on September 28. Construction and building permits have been submitted. Pending permit approvals, mobilization will begin in late October. Work is anticipated to take 180 calendar days. The play equipment has been fabricated and was received in September.
  • April 2023
    The Invitation to Bid was issued in March and the bid opening is scheduled for early May.  The playground equipment colors were finalized.
  • February 2023
    The play equipment purchase order was approved in January. Play equipment colors are being finalized. The play equipment will be released into production later this month and will take approximately six months to manufacture and deliver.  The City's Purchasing Department is in the final stages of preparing the Invitation to Bid (ITB) for advertisement next month.
  • August - December 2022
    Staff will work on the solicitation for the Invitation to Bid (ITB). The project schedule has been updated to reflect current market lead times for the manufacturing of playground equipment, which has been affected by supply chain issues.
  • April - December 2021
    J2 Engineers have completed the engineering plans. The plans have been approved by the City.  The project will now be procured for construction services.
  • January - March 2021
    J2 Engineers will continue work on the engineering plans and obtain regulatory approvals for the project.
  • November - December 2020
    J2 Engineers completed the site survey, tree inventory and utility locating.
  • October 2020
    The engineering design contract was awarded to J2 Engineers.
  • March 2020
    The City's Purchasing Department is in the process of re-bidding the engineering design contract.  
    The updated project scheduled is noted above.
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...