King-Beauregard Intersection Improvements Project

The City is constructing new turn lanes, median islands, upgraded sidewalks and enhanced crossings at the intersection of King St., N. Beauregard St., and S. Walter Reed Dr.
Page updated on Aug 29, 2025 at 9:50 AM

Contact

 

Tafesse T. Gyes, PE, CCM
Construction Operations Manager
Project Implementation
703.746.4051

 

Ryan Knight, PE
Division Chief, Transportation Engineering Division
Transportation & Environmental Services
703.746.4225

 

MEDIA INQUIRIES

Office of Communications and Community Engagement
newsroom@alexandriava.gov
703.746.3969


TRANSLATION SERVICES

Ver esto en español 
ይህንን በአማርኛ ይመልከቱ 
عرض هذا باللغة العربية

If you prefer communication in another language, free interpretation and translation services are available to you, please email 
LanguageAccess@alexandriava.gov or call 703.746.3960.

 

ACCESSIBILITY

For reasonable disability accommodation, contact Tafesse T. Gyes at tafesse.gyes@alexandriava.gov or call 703.746.4051, Virginia Relay 711.

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Overview

Map of Alexandria with red box indicating the project location

Phase: Construction

Status: Active

Location: Beauregard

Managing Dept.: Project Implementation

Sponsor Dept.: Transportation & Environmental Services

Project Description

The King Street and N. Beauregard Intersection Improvements project redesigns the intersection to improve safety for roadway users. The reconfiguration will include new turn lanes, median islands, upgraded sidewalks and enhanced crossings. The project not only enhances capacity for people driving, but improves safety for people walking, biking, and riding transit. 

Street view of King-Beauregard intersection
Second street view of the King-Beauregard intersection
Third street view of King-Beauregard intersection
Single page view of planned improvements at the intersection of King St. and N. Beauregard St.
King Street Improvements Striping Plan
King Street Improvements Striping Plan
King Street Improvements Striping Plan
King Street Improvements Striping Plan
King Street Improvements Striping Plan
of
Grid View Close Modal
Street view of King-Beauregard intersection
Second street view of the King-Beauregard intersection
Third street view of King-Beauregard intersection
Single page view of planned improvements at the intersection of King St. and N. Beauregard St.
King Street Improvements Striping Plan
King Street Improvements Striping Plan
King Street Improvements Striping Plan
King Street Improvements Striping Plan
King Street Improvements Striping Plan

Schedule

Design (Active): Q2 2022 - Q3 2025

Construction: Q1 2026 - Q4 2026

Design Phase

The design was revised in 2022 to include improvements that would benefit all users of the roadway. The project design includes various intersection improvements along King Street, between N. Hampton Drive and Chesterfield Road. Elements of the design include the following…

  • Lane realignment to encourage safer turning speeds, easier transitions through the intersection, and allow for medians within the intersection,
  • Removing the right turn lane median on the northwest corner of the N. Beauregard Street intersection to encourage safer turning speeds and improve pedestrian safety crossing the intersection
  • Adding striped out medians on King Street at the Chesterfield Street intersection and the 28th Street intersection to provide more space for pedestrians to wait if they cannot cross the full distance of the intersection.
  • Adding striped out and concrete medians with pedestrian cut outs on all legs of the N. Beauregard Street intersection to provide more space for pedestrians to wait if they cannot cross the full distance of the intersection.
    • It is important to note, the striped-out medians on King Street could be used for an additional left turn lane if congestion levels deem warranted in the future.
  • Extending the left turn lane for the westbound approach of King Street at the N. Beauregard Intersection to enhance capacity along King Street.
  • Upgrading the traffic signal infrastructure within all King Street intersection between Chesterfield Road and N. Hampton Drive
  • Upgrading the curb ramps along King Street, between Chesterfield Street and N. Hampton Street to be compliant with ADA requirements.

Design is finalizing and is slated to be complete Late Summer 2025. 

Construction Phase

Once VDOT approves the City to move forward with construction, the City will begin the procurement process. 

Construction is slated to Complete Q4 2028.

Funding

This project is primarily funded through...

  • The Federal Highway Administration’s (FHWA’s) Congestion Mitigation and Air Quality (CMAQ) Improvement Program
  • The Federal Highway Administration’s (FHWA’s) Regional Surface Transportation Program (RSTP)

Total Project Budget: $21M

Council Progress Reports

  • Capital Improvement Program
  • Infrastructure
  • Mobility
  • Pedestrians
  • Sidewalks
  • Streets
  • Traffic
  • Traffic Safety
  • Transportation
  • Transportation
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...