Mount Vernon Dual Culvert Replacement Project

The Mount Vernon Dual Culvert Improvement project aims to mitigate localized flooding by upgrading the storm sewer system in the area bound by Mount Vernon Avenue, Edison Street, and W. Reed Avenue.
Page updated on February 27, 2026 at 1:25 PM

Stormwater Management

  • Stormwater Quality
  • Flood Action Alexandria
  • Flooding & Drainage
  • Stormwater Utility Fee
  • Stream Restoration
  • Chesapeake Bay
  • Sanitary Sewers
  • Illicit Discharges

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Overview

Mt. Vernon culvert project map

The Mount Vernon Dual Corrugated Metal Pipe (CMP) Culvert Improvement project aims to mitigate localized flooding by upgrading the storm sewer system in the vicinity of Mount Vernon Avenue, Edison Street, and W. Reed Avenue (as shown in the project vicinity map above). The main work includes the improvement of the CMP pipes, improving flow through the pipes, and relocating storm drain inlets. Other work may include shifting the storm sewers coming from Mount Vernon Avenue to a more suitable position between two buildings between Mount Vernon Avenue and Edison Street. 

• Status: In design

• Total Cost: $2,500,000 (est.)

• Funding Source: 50% Virginia Community Flood Preparedness Fund (CFPF) and 50% City funding

project map screen shot .jpg

Capital Projects

Check the status of the City's flood mitigation projects using this interactive map tool.

Background

The City of Alexandria is experiencing more frequent and severe flash flooding from extreme precipitation events that have occurred more frequently in the last few years. These flash flood events damage residential and commercial properties, impact critical assets, and cause day-to-day disruptions and economic losses. The City is implementing resilient stormwater system upgrades informed by the City of Alexandria Storm Sewer Capacity Analysis (CASSCA) and neighborhood investigations, as well as making spot improvements to high-priority flood risk areas, along with accelerated frequent operations and maintenance under the Flood Action Alexandria program.

Progress Update

City staff reviewed the 90% design plans for the Mount Vernon Dual Culverts Replacement Project and provided design comments earlier this fall. As part of the design progress, it was determined that north culvert needs to be cured-in-place using polyethylene technology and rehabilitation of the other culvert. Subsequently, City held a review meeting on December 10, 2025 discussing comments and how plans will be revised. The City also discussed a need for right of entry agreement regarding access to portion of project area for which the City does not have an easement. 

In parallel with the design progress, the City team conducted the first community meeting with residents, businesses and other stakeholders in the project area. The meeting was held on November 3, 2025, at the Leonard “Chick” Armstrong Recreation Center. The City team presented an overview of the project’s goals, design plans, anticipated construction impacts, and the project schedule. The meeting also answered community questions. 

Project Stages

Investigation

This neighborhood in the vicinity of Edison Street and West Reed Avenue, located off Mount Vernon Avenue, experienced significant flooding from heavy storms that took place between 2019 and 2020. The City conducted neighborhood investigations, engineering assessments, and analysis of the storm sewer network in this area beginning in early 2021. The Mount Vernon Dual CMP Culvert project was identified as a spot improvement project under the Flood Action Alexandria program.

The Flood Action Alexandria team conducted field investigations in May 2023. A topographical survey and geotechnical investigations were completed in June 2023.

Design procurement

AECOM was selected as the project’s design consultant and tasked with developing an efficient, effective, and constructible design.

The consultant will design a solution to reduce flooding, to the maximum extent practical, between Mount Vernon Avenue and the outfall east of Edison Street.

Design

Design stages

The design consultant is modeling and analyzing two alternatives to improve the conveyance of stormwater. The 30% construction plans are anticipated by mid-August 2023.

On-Site: Photos from the Mount Vernon Dual Culvert Replacement Project

Progress on the Mount Vernon Dual Culvert project.

Contractors for the City drill into Mount Vernon Avenue for culvert project
Photo of the Mt. Vernon Avenue culvert headwall
A contractor for the City sealing a boring hole after completing the geotechnical investigation. (City of Alexandria)
of
Grid View Close Modal
Contractors for the City drill into Mount Vernon Avenue for culvert project
Caption: Contractors for the City drill into Mount Vernon Avenue and the outfall east of Edison Street as part of geotechnical investigation on June 27, 2023. A total of five soil borings were drilled at the site by the City’s contractor along the route of the existing Mount Vernon culvert system. The goal of the investigation was to determine the subsurface conditions along the proposed storm sewer pipes and manholes. The results of the analysis will help the city determine the appropriateness of proposed design alternatives. (City of Alexandria)
Photo of the Mt. Vernon Avenue culvert headwall
Dual culverts at headwall
A contractor for the City sealing a boring hole after completing the geotechnical investigation. (City of Alexandria)
A contractor for the City sealing a boring hole after completing the geotechnical investigation. (City of Alexandria)

News and Public Announcements

Project notices

  • May 23, 2023: The first notice was sent to nearby residents of the project regarding the project survey and geotechnical investigation
  • September 23, 2024: Survey crews are scheduled to perform an onsite assessment of City stormwater infrastructure. Notices will be sent to residents prior to the start of onsite work.. 

Community meetings

• June 24, 2023: The project team presented the project to the Hume Spring Civic Association.

• October 19, 2023: Upcoming public meeting.

Contact

Haweni Gobena
Sponsor Project Manager
Department of Transportation and Environmental Services
703.746.4286
haweni.gobena@alexandriava.gov
 

For the community:  

Wael Eltayeb, P.E.  
Project Manager
703.746.4217 (Office)
703.512.6253 (Direct)
Wael.eltayeb@alexandriava.gov  

For the media:

Zhanea Gillespie
Communications Officer, Flood Action Alexandria
703.746.4015
zhanea.gillespie@alexandriava.gov 

Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal
City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...