King and Strand Sanitary Sewer Replacement Project

Page updated on February 27, 2026 at 11:34 AM

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Current Phase: Planning

Sponsor Project Manager: Dung (Young) Huynh, Department of Transportation and Environmental Services

Managing Project Manager: Lindsay Burleigh, Department of Project Implementation

King and Strand Location Map

Project Description

This project replaces 94 feet of existing 6-inch and 8-inch sanitary sewer on Strand Street between King Street and Wales Alley. The two sewer lines are in poor structural condition based on CCTV records. The pipe condition is impossible to repair by lining and requires replacement.

Initially, the City was planning to use the on-call contractors which would require minimal design.  Because of the proximity of these sewer lines to the Waterfront Project, senior City staff instead decided to incorporate this project into the Waterfront Project. Until the project is fully absorbed into the Waterfront Project, the project status will be on hold.

Project Funding

Project Budget

Total Budget: $560,000

Planning: $0 (Sewer inspection was completed as part of the Old Town Condition Assessment Project.)

Design: $140,000

Construction (Including CMI and Construction Contingency): $420,000

Funding Breakdown

This project is funded using Sanitary Sewer Enterprise Fund revenues and is programmed in the City's Capital Improvement Program.

Project Schedule

To be determined as part of the Waterfront Project.

Planning Phase

Planning Overview

  • Condition Assessment – Inspected two sanitary sewer segments at this area using CCTV camera per NASSCO (National Association of Sewer Service Companies) guidelines to document internal structural and operation and maintenance (O&M) conditions.
  • Replacement Recommendation – Reviewed inspection reports and photos and it was determined that the two sewer segments at King/Strand were at a risk of failure and were proposed for replacement.
  • Cost Estimate – a planning level cost estimate was performed for design and construction services.

Planning Public Outreach

Public outreach for the King and Strand Sanitary Sewer Replacement Project has not yet been scheduled. Please check the webpages at a later date for updates.

Contact

Dung Huynh

Civil Engineer III

City of Alexandria, Virginia

T&ES/Sanitary Infrastructure Division

 (703) 746-4052 or 4014

Dung.huynh@alexandriava.gov

Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal
City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...