Del Ray West Lateral Rehabilitation

Page updated on April 26, 2024 at 12:52 PM

Share

Share on Twitter Share on Facebook
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Current Phase: Planning

Sponsor Project Manager: Lu Zhang, Transportation & Environmental Services

Managing Project Manager: Anup Gautam, Project Implementation

Del Ray West Map

Project Description

The Del Ray West Lateral Rehabilitation project provides for the inspection and rehabilitation of City-owned portions of sanitary sewer laterals in the Del Ray West area, generally located between Commonwealth Avenue and Russell Road from West Glebe Road to King Street. This work is being done as part of the City's Sanitary Sewer Asset Renewal Program.

This project is currently in the planning phase. Planning phase activities consist of closed circuit television (CCTV) of lateral sewers. Inspection data collected is then reviewed to determine what laterals require rehabilitation, with most of the rehabilitation being trenchless (no digging). The planning phase is being managed by the Department of Transportation and Environmental Services' Sanitary Infrastructure Division. Following planning, the project will be transferred to the City's Department of Project Implementation for design and construction.

This project extends the useful life of the existing sanitary sewer system, reduces the amount of infiltration and inflow (I&I) that enters the sanitary sewer system and reduces the need for emergency repairs.

Project Funding

Project Budget

Total Budget: $2.5 million

Planning Phase: $0 (Planning level costs included as part of the Del Ray West Manhole and Mainline Rehabilitation)

Design Phase: $100,000

Construction Phase: $2.4 million

Funding Breakdown

Funding for the Sanitary Sewer Asset Renewal Program comes from the City's Capital Improvement Program for Sanitary Sewers.

Project Schedule

Planning: June 2022 - October 2024

Design: October 2024 - December 2025

Construction: January 2026 - January 2027

Planning Phase

Planning Overview

 

  • Field Inspection/ Condition Assessment - Inspected City-owned portions of lateral sewers using CCTV camera per National Association of Sewer Service Companies (NASSCO) guidelines to document structural and operation and maintenance (O&M) conditions of each asset.
  • Rehabilitation Recommendation - Reviewed inspection reports and photos to determine sewer assets requiring rehabilitation and proper rehabilitation technology.
  • Cost Estimate - A planning level cost estimate was performed for design and construction services.

Planning Public Outreach

Residents and businesses are notified of the project through public signage, along with door hangers for when work is occurring in their area.

Contact Us
Alex311 | 703.746.4311
Follow Us
  • Facebook
  • Twitter
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Emergency Hotlines
  • Social Media
  • Privacy & Legal
  • FOIA Requests
  • Departments
  • Jobs
  • Payments

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...