Skip to main content
You're logged in with MyAlex  |  Logout

City of Alexandria, VA

Search results cleared

Include archived pages
Most of the content here is written in English. Translate your search to find more content? Translating "" to English... Searching for English phrase ""
  • Live
  • Play
  • Services
  • Business
  • Government
  • Projects & Plans
  • Calendar
  • I want to…

King and Strand Sanitary Sewer Replacement Project

Page updated on May 21, 2026 at 2:54 PM

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Current Phase: Planning

Sponsor Project Manager: Qais Ayubi, Department of Transportation and Environmental Services

Managing Project Manager: Lindsay Burleigh, Project Implementation

King and Strand Location Map

Project Description

This project involves the replacement of approximately 92 linear feet of existing 6-inch sanitary sewer and 2 linear feet of existing 8-inch sanitary sewer located on Strand Street between King Street and Wales Alley. The sewer segments were evaluated through CCTV inspection records and determined to be in poor structural condition. Based on the observed defects and pipe condition, full replacement is required to restore structural integrity, maintain reliable sewer service, and extend the useful life of the sanitary sewer system.

The planning phase has been completed, and the project will proceed through the design and construction phases. Design is anticipated to begin in late 2026, with construction expected to begin early 2027.

Project Funding

Project Budget

Total Budget: $650,000

Planning: $0 (Sewer inspection was completed as part of the Old Town Condition Assessment Project.)

Design: $140,000

Construction (Including CMI and Construction Contingency): $510,000

Funding Breakdown

This project is funded using Sanitary Sewer Enterprise Fund revenues and is programmed in the City's Capital Improvement Program.

Project Schedule

  • Planning: May 2024 - June 2026 (25 months) (The project was initially part of Waterfront Plan but is now separate)
  • Design: July 2026 - June 2027  (12 months)
  • Construction: July 2027 - June2028 (12 months) - Includes time for ITB preparation and contract award

Planning Phase

  • Condition Assessment – Inspected two sanitary sewer segments at this area using CCTV camera per NASSCO (National Association of Sewer Service Companies) guidelines to document internal structural and operation and maintenance (O&M) conditions.
  • Replacement Recommendation – Reviewed inspection reports and photos and it was determined that the two sewer segments at King/Strand were at a risk of failure and were proposed for replacement.
  • Cost Estimate – a planning level cost estimate was performed for design and construction services.

Public outreach for the King and Strand Sanitary Sewer Replacement Project has not yet been scheduled. Please check the webpage at a later date for updates.

Contact

Qais Ayubi

City of Alexandria, Virginia

T&ES/Sanitary Infrastructure Division

 (571) 302-2114 

Qais.Ayubi@alexandriava.gov

Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal
City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...