East Mason Avenue Curb Inlets

The City is planning drainage enhancements to address flooding on East Mason Avenue.
Page updated on Jul 19, 2024 at 5:21 PM

Contact

Camille Liebnitzky, PE, ENV SP
Environmental Engineer IV, Stormwater Utility Manager
Department of Transportation & Environmental Services 
703.746.4089

 

Media Inquiries

Office of Communications and Community Engagement
newsroom@alexandriava.gov
703.746.3969

 

TRANSLATION SERVICES

Ver esto en español 
ይህንን በአማርኛ ይመልከቱ 
عرض هذا باللغة العربية

If you prefer communication in another language, free interpretation and translation services are available to you, please email 
LanguageAccess@alexandriava.gov or call 703.746.3960.

 

ACCESSIBILITY

For reasonable disability accommodation, contact Camille Liebnitzky at Camille.Liebnitzky@alexandriava.gov or call 703.746.4089, Virginia Relay 711.

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Phase: Planning

Status: Active

Location: Potomac West

Managing Dept.: Project Implementation

Sponsor Dept.: Transportation & Environmental Services

Map of Alexandria indicating the location of E. Mason Ave.
View in Google Maps

Project Description

The City of Alexandria is improving the storm sewer infrastructure along E. Mason Avenue between Mt. Vernon Avenue and DeWitt Avenue to reduce neighborhood flooding from intense rain events. The project was identified following an investigation of the storm drain networks, flooding issues and drainage patterns. Proposed improvements include replace the existing curb inlets featuring two openings located on the north and south sides of E. Mason Avenue with redesigned larger curb inlets featuring three openings. The three-inlet system can capture and convey a larger quantity of storm water into the sewer system and will reduce the likelihood or magnitude of localized flooding.

Note: This project is contingent on the Hooffs Run Culvert Bypass project and successful co-location of the new design with other existing utilities in the right-of-way.

Funding

Project Budget: $60,000

CIP Section: Stormwater Management

Learn more about the City of Alexandria's Fiscal Year Budget.

Schedule

Note: Work on this project has not yet started. The following schedule is preliminary and subject to change.
  • Planning: July 2025 - July 2026    
  • Design: July 2026 - July 2027    
  • Construction: July 2027 - July 2028

Planning

Planning Update

This project is scheduled to start planning in FY26. There is currently no active work taking place at this time.

 

Sponsor Program

Flood Action Alexandria logo

This project is part of the Flood Action Alexandria program. In response to more frequent, intense climate-change-induced storm events, the City of Alexandria launched Flood Action Alexandria, a multipronged program to help address flooding issues in our community. 

  • Capital Improvement Program
  • Flooding
  • Infrastructure
  • Sewers
  • Stormwater
  • Water
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...