Oakland Terrace-Timber Branch Channel Wall Reconstruction
Page updated on Jan 2, 2024 at 5:05 PM
WARNING: You have chosen to translate this page using an automated translation system.
This translation has not been reviewed by the City of Alexandria and may contain errors.
Project Summary
Phase: Construction
Status: Active
Location: North Ridge/Rosemont
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City of Alexandria is replacing approximately 205 linear feet of existing concrete retaining wall with a vegetative reinforced revetment and bioengineered soil. Additional stream stabilization measures will include clearing out invasive species and planting native vegetation on the stream bank in opposition of the proposed vegetated wall.
Funding
This project is funded by Capital Improvement Program (CIP) stormwater management funds.
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Design: September 2020 - December 2022
- Construction: January 2023 - October 2024
- Construction Site Activity: January 2024 - October 2024
Construction
Construction Hours
General Construction Activity:
- Monday-Friday: 7 a.m.-6 p.m.
- Saturday: 9 a.m.-6 p.m.
Construction Impacts
Parking
- Curbside parking adjacent to the project will be temporarily suspended to provide site access.
Street Closures
- Periodic lane closures on W. Timber Branch Pkwy. and Oakland Terr. during construction hours.