Clifford Avenue, Fulton Street and Manning Street Storm Sewer Improvements
Project Summary
Phase: Design
Status: Active
Location: Potomac West
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The Clifford Avenue, Fulton Street and Manning Street (CFM) Storm Sewer Improvements Project will provide flooding mitigation to townhouses along the 3000 block of Fulton Street and Manning Street. The alley bound between the two streets will be re-built to channelize surface flow and improve drainage. Inlets and underground storage will be installed to capture and attenuate stormwater runoff. Utility impacts will be identified and resolved during the design phase.
Progress Update
In November, The City accepted the preliminary design and coordinated with the City's interdepartmental review team.
The City approved continuing with the design, and the 30 percent design phase is expected in December.
Additional topographic data to support the proposed work at the intersection of Commonwealth Avenue and Clifford Avenue will be collected in December.
Project staff are working to plan a community meeting in February 2025 following a complete review of the 30 percent design. Here the City will present the proposed scope of work, the benefits to the community, and the potential impacts associated with construction activities.
Previous updates may be found under the "Design Phase Background" dropdowns listed below.
Design Phase Background
November 2024
In early September, the City awarded a design services contract to AECOM to develop construction drawings for the proposed project. A public project kickoff announcement was presented at the Flood Mitigation and Stormwater Utility Advisory Committee meeting on September 18th at City Hall. Subsequently, the City issued formal Notice to Proceed on the design contract.
In late October, the City completed topographic survey of the alleyway and Preliminary Design for the proposed improvements. Following the distribution of work notices, utility test pits and soil sampling were completed. The results are being assessed by the City to determine design conflicts and the suitability of the foundation soils to support the proposed improvements. In November, the City will complete review of the preliminary design package and begin 30% design.
A public community meeting is anticipated for February 2025 following the completion of the 30% concept design phase. At the public community meeting, the City will present the proposed project’s scope of work, the benefits to the community, and the potential impacts due to construction activities
Prior to the award of the contract, the City completed site survey to expedite design development and reduce contract costs.
Funding
Project Budget: $830,000
Funding Source:
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: January 2023 - October 2023
- Design: October 2023 - September 2025
- Construction: September 2025 - February 2026
Project Phases
Planning
During the planning phase, the project team characterized the types of impacts experienced in the community and determined goals for the project. Based on project goals, a feasible solution was scoped and a rough order of magnitude cost estimate was developed based on conceptual drawings. These materials were used to secured a federal grant to support the work.
Design
Design Procurement
The City will procure engineering design services for the proposed work through an existing on-call services contract. These services include topographic survey, utility locating services, cost estimating services and engineering design services.
More information about the City's procurement processes and policies can be found on the Finance Department's Purchasing webpage.
During the design phase, the project team will perform in-field data collection and develop technical construction documents to deliver the proposed project scope. These construction documents will be incorporated into a public solicitation for construction services to build the project.
Community Engagement
The City issued a work notice to residents in early October prior to the utility test pits and geotechnical testing.
The City intends to hold a public kickoff meeting for the project following successful negotiation of design services. An additional public meeting will be held at the mid-point of design to provide an update on the design scope, schedule and progress.
Sponsor Program
This project is part of the Flood Action Alexandria program. In response to more frequent, intense climate-change-induced storm events, the City of Alexandria launched Flood Action Alexandria, a multipronged program to help address flooding issues in our community.