Skyhill Road Stormdrain Extension

The City is extending the storm sewer system serving Skyhill Rd. to improve drainage during wet weather events.
Page updated on May 22, 2024 at 5:39 PM

Contact

Camille Liebnitzky, PE, ENV SP
Environmental Engineer IV, Stormwater Utility Manager
Department of Transportation & Environmental Services 
703.746.4089

 

Media Inquiries

Office of Communications and Community Engagement
newsroom@alexandriava.gov
703.746.3969

 

TRANSLATION SERVICES

Ver esto en español 
ይህንን በአማርኛ ይመልከቱ 
عرض هذا باللغة العربية

If you prefer communication in another language, free interpretation and translation services are available to you, please email 
LanguageAccess@alexandriava.gov or call 703.746.3960.

 

ACCESSIBILITY

For reasonable disability accommodation, contact Camille Liebnitzky at Camille.Liebnitzky@alexandriava.gov or call 703.746.4089, Virginia Relay 711.

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Phase: Planning

Status: Active

Location: Taylor Run/Duke Street

Managing Dept.: Project Implementation

Sponsor Dept.: Transportation & Environmental Services

Map of Alexandria with a red box indicating the location of the Skyhill Rd. Stormdrain Extension project.
View in Google Maps

Project Description

The City is extending the storm sewer system serving Skyhill Rd. to improve drainage during wet weather events. Following an initial survey of the West Taylor Run neighborhood, the City determined the installation of additional sewer pipe and new inlets along Skyhill Road could substantially improve the capture of stormwater run-off and reduce flooding neighborhood flooding.

Funding

Project Budget: $350,000

CIP Section: Stormwater Management

Learn more about the City of Alexandria's Fiscal Year Budget.

Schedule

Note: Work on this project has not yet started. The following schedule is preliminary and subject to change.
  • Planning: July 2025 - July 2026
  • Design: July 2026 - July 2027
  • Construction: July 2027 - June 2028

Planning

Planning Update

The Planning phase is scheduled to begin in July 2025. Additional information will be provided as the project progresses.

 

Sponsor Program

Flood Action Alexandria logo

 

 

 

 

 

This project is part of the Flood Action Alexandria program. In response to more frequent, intense climate-change-induced storm events, the City of Alexandria launched Flood Action Alexandria, a multipronged program to help address flooding issues in our community. 

  • Capital Improvement Program
  • Flooding
  • Infrastructure
  • Public Facilities
  • Sewers
  • Stormwater
  • Water
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...