Union Street Paving Project 2021
Project Summary
The City of Alexandria, Transportation and Environmental Services, Public Works Services Division, is repaving Union Street starting August 23, 2021. The repaving of Union Street has been phased into five (5) sections to provide clear impacts of work within a specific date range(s), as provided in the Planned Paving Schedule.
Current Progress
Prior to the repaving of Union Street, the City has been in the process of making other repairs and improvements along the edge of the roadway. These improvements have and will continue to involve curb and gutter, selected handicap ramps for access and selected pedestrian safety improvements. The work is intended to continue during the phased paving and may continue after the paving is completed.
Planned Paving
PHASE 1
The first phase of milling and paving will include Union Street, from Pendleton Street to Princess Street. The scheduled dates are August 23, 2021 and will conclude August 24, 2021.
PHASE 2
The second phase will include, from Princess Street to Cameron Street. It is anticipated to begin on August 24, 2021 and conclude August 25, 2021.
PHASE 3
The third phase will include, from Cameron Street to Prince Street. It is anticipated to begin on August 25, 2021 and conclude August 26, 2021.
PHASE 4
The fourth phase will include, from Duke Street to Franklin Street. It is anticipated to begin on August 26, 2021 and conclude August 30, 2021.
PHASE 5
The fifth phase will include, from Prince Street to Duke Street. It is anticipated to begin on August 30, 2021 and conclude August 31, 2021.
Scheduling is highly dependent on weather conditions.
HOURS OF OPERATION
Work will begin each morning at 7:00 am and last until approximately 3:30 pm each day as indicated within the Planned Paving Schedule. The Contractor may be moving equipment to and from staging areas prior to this time, so additional delays may occur.
Work is not planned for holidays and/or weekends. Work will also stop due to inclement weather or high tide from the Potomac River.
CONSTRUCTION IMPACTS
The work will occur in two-block sections with the intent to complete each section within two days. For us to move efficiently and quickly without delays, we are asking for everyone’s help with the following:
- Be attentive to the temporary no parking signs that will be placed prior to paving a particular block(s)
- In event of weather delays, temporary no parking signs will be modified
- All vehicles shall be moved off the street prior to 6:30 am each morning.
- No parking of private vehicles (even short stopping) in the current section that is being paved
- Please pay attention to detours, as traffic in the immediate and surrounding area will to be re-directed.
- City T&ES staff will be on the scene for the duration of the project.
Frequently Asked Questions (FAQs)
Q1: Will repaving equipment be left on the street?
A1: The repaving equipment will have a designated staging area.
Q2: Will the entire street be closed within a 4 to 5 block repaving segment?
A2: No. We plan to close half the street at a time per 1 to 2 block repaving segments. There will be guidance on how through traffic should proceed during the repaving work. Most traffic will be redirected, with an exception of local residents, emergency vehicles, delivery vehicles and transportation vehicles.
Q3: Will a City employee be available to answer questions?
A3: City staff inspectors will be on-site during the repaving work.
PROJECT CONTACT
For more information, or with questions about the paving project, please contact Public Works Capital Program Manager Mary Alice Winston at maryalice.winston@alexandriava.gov