Hotel Indigo Conservation Update: PEG treatment continues
PEG treatment continues, with the the ship's return now scheduled for Fall 2028.
Page updated on December 12, 2025 at 2:30 PM
XWARNING: You have chosen to translate this page using an automated translation system.
This translation has not been reviewed by the City of Alexandria and may contain errors.
PEG Treatment Continues
December 2025
Conservation work on the Hotel Indigo Ship remnant continues at Texas A&M University’s Conservation Research Lab (CRL). However, due to unanticipated setbacks the project timeline has shifted. The vats for soaking timbers in polyethylene glycol (PEG) are located outside. Continuous heavy rains over the spring and summer diluted the concentration of PEG in the basins holding the Hotel Indigo Site ship timbers. Staff at the CRL determined that the best course of action would be to restart the PEG soaking process, leading to a delay in the project schedule. The ship remnant is now anticipated to return to Alexandria in Fall 2028.